Report for August 2017

Report Date
August 2017

Section One: Programme Commentary, RAG and Resources Update

Commentary:

This new session 17/18 has one ongoing projects:

One project was closed this month:

The status for SCEP02 -Virtual Edinburgh PM Consultancy and Support   is AMBER due the ongoing work into defining its scope with regard to CityDeal. The overall status of the CSE programme is AMBER.

Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.

 

Forward Look - August 2017:

 

Resources to end August 2017:

 

 

Section Two: Projects Not Started

Project Info Programme Manager's Commentary
CSE has a budget of 150 ring fenced days for 17/18,  possible projects are being considered and allocations yet to be confirmed.  

 

Section Three: Projects in Progress

Project Info Project Managers Commentary

SCEP02 Virtual Edinburgh PM Consultancy and Support

Category: Discretionary

Milestones

N/A

 

RAG Status

AMBER

Report by Morna Findlay for August 2017

Achievements this period

No report provided

Issues
Next steps

SCE011: ExamOnline Trial

Category: Discretionary

Milestones

N/A

 

RAG Status

BLUE

Report by Muriel Mewissen for August 2017

Achievements this period
Issues
  • None
Next steps
  • N/A

 

Section Four: Closed or Withdrawn Projects

Project Info Project Manager's Commentary
SCE011 ExamOnline Trial This project started in October 2017. This project was closed on 31 August 2017. The Completion Report is now available.

 

Section Five: Programme Meeting Minutes

Date Comments
21 Aug 2017 Programme Review for July 2017 - meeting minutes

 

Programme Info

Documentation

Not available.