Report for August 2017
- Report Date
- August 2017
Section One: Programme Commentary, RAG and Resources Update
Commentary:
This new session 17/18 has one ongoing projects:
One project was closed this month:
The status for SCEP02 -Virtual Edinburgh PM Consultancy and Support is AMBER due the ongoing work into defining its scope with regard to CityDeal. The overall status of the CSE programme is AMBER.
Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.
Forward Look - August 2017:

Resources to end August 2017:

Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
|---|---|
| CSE has a budget of 150 ring fenced days for 17/18, possible projects are being considered and allocations yet to be confirmed. |
Section Three: Projects in Progress
| Project Info | Project Managers Commentary |
|
SCEP02 Virtual Edinburgh PM Consultancy and Support Category: Discretionary MilestonesN/A
RAG StatusAMBER |
Report by Morna Findlay for August 2017 Achievements this periodNo report provided IssuesNext steps |
|
Category: Discretionary MilestonesN/A
RAG StatusBLUE |
Report by Muriel Mewissen for August 2017 Achievements this period
Issues
Next steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Manager's Commentary |
|---|---|
| SCE011 ExamOnline Trial | This project started in October 2017. This project was closed on 31 August 2017. The Completion Report is now available. |
Section Five: Programme Meeting Minutes
| Date | Comments |
|---|---|
| 21 Aug 2017 | Programme Review for July 2017 - meeting minutes |