Report for October 2016
- Report Date
- October 2016
Report by Muriel Mewissen for Bruce Nelson (Portfolio Owner)
Section One: Programme Commentary, RAG and Resources Update
Commentary:
The CSCE Programme / Portfolio has a budget of 211 days for 2016/17.
A new project, SCE011 - ExamOnline Trial, has started this month to trial an online assessment application in the school of Biology. This short project has been allocated 10 days of core finding. The trial will take place on 16 November 2016. Outcomes and evaluation of the trial will be done in December.
SCE010 Athena Swan Reporting Improvements: This project is close to completion. A last minute change in process has been identified during the deployment. This requires a configuration change to be carried out by Payroll. The new LIVE date is 1 Decmeber 2016. This project is AMBER due to this delay.
SCEP02 Virtual Edinburgh PM consultancy and Support: This project provides PM consultancy to the Edinburgh CityScope programme of works and used 9 days of its 50 days allocation in the 16/17 budget. The Innovation project API017 Edinburgh CityScope Foundations constitutes the second phase of this programme and will end in February 2017. The project is actively working on securing funding for the following phases. A small amount of funding for this year Innovation Fund has been secured for the coming year.The project status is GREEN.
We note that an initial conversation has taken place with the school of Chemistry who are considering the use of the project website as a project management tool for internal projects.
Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.
Of interest: COM032 - Rollout Academic Timetable Integration with Office 365 Calendar which is due to start soon.
Forward Look - October 2016

Resources to end October 2016
NB: SCE011 is not showing the correct number of resources in the report below (30 instead of 10). This has been corrected in teh system and will appear correctly next month.

Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
|
AP67-073 16/17 Ring Fenced Allocation for CSCE GREEN |
128 days of core funding remains to be allocated (out of 150 days). 12 days have been allocated to SCE010, and 10 days to SCE011. |
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||
SCE010 (AP56-925)Athena Swan Reporting Improvements
Category: Discretionary Milestones
RAG Status AMBER |
Report by Susan Duff for October 2016 Achievements:
Issues:
Next Steps:
Amber status is due to agreed delay to closure of project being greater than one month
|
||||||||
SCEP02:Virtual Edinburgh PM Consultancy and Support
Category: Discretionary Milestones n/a RAG Status GREEN |
Report by Morna Findlay for October 2016 Achievements:
Issues:
Next Steps:
|
||||||||
SCE011: ExamOnline Trial
Category: Discretionary Milestones
RAG Status GREEN |
Report by Muriel Mewissen for October 2016 Achievements this period
Issues
Next steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary | |
|
N/A |
Projects in the CSCE programme for 16/17 are currently in progress or are yet to start. |