November 2015

Report Date
November 2015

Report by Sheila Fraser for Bruce Nelson (Portfolio Owner)

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

Commentary

The CSCE Programme / Portfolio is overall GREEN, as the work agreed is expected to be able to be delivered within the current year.

Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.

SCE007, Digitising Scotland Planning: draft documents developed. This is AMBER due to previous delays for 3-year planning, and additionally for delay in being able to speak with NRS due to political sensitivities. Scope, estimate and milestones have been changed to resolve this; the resources table below does not yet reflect this recently agreed reduction in estimate from 15d to 11d (purple circle).

SCE008, University Seminar Site Enhancements: user acceptance testing completed, deployment delayed slightly and now complete. Project due to close in December.

SCE009, Virtual Edinburgh Scoping: project brief approved and workshops and meetings arranged to enable the technical evaluation phase to be undertaken in December/January.

AP56-034 Ring Fenced Allocation for CSCE started the year at 150d. Of this a) 25d has been transferred to fund RES057, the RMAS PURE integration, which is currently suspended and expected to restart in January 2016 b) 22d has been transferred to PPP001, Parental calculations analysis and Athena SWAN requirements, to fund the Athena SWAN analysis elements and c) 35d has been transferred to SCE008 University Seminar Site Enhancements and d) 10d has been transferred to SCE009 Virtual Edinburgh Scoping. Please see section Projects Not Started, AP56-034 15/16 Ring Fenced Allocation for CSCE for further details on use of this remaining 58d allocation.

Resources

The agreed budget is 140d, reflecting the transfer of 10d to PPP001. SCEP01 is showing 26d of effort to complete this year which is expected to be sponsor-funded as project management support for the Virtual Edinburgh programme, causing the balance to show as -25d (red circled). The corresponding budget increase will resolve the negative balance once the project is initiated in January 2016.

RAG & Forward Look

Notes on Current Plans for 16/17

  • The work on the Chemistry Scientific Instrument Management Business Case in 14/15 has found that if the recommendations are followed then no work from IS Applications would be needed in 15/16, however potential integration work with Finance and Grouper may be needed in 16/17.
  • As the University Seminar Site is still in pilot phase, and will be until summer 2016, time must be set aside in 16/17 to either turn the pilot into a full service with proper documentation and agreed support levels, or to decommission the site.

Section Two: Projects Not Started

Project InfoProgramme Manager's Commentary

AP56-034 15/16 Ring Fenced Allocation for CSCE

GREEN

There is now expected to be a matching demand for the SCE Ring-Fenced days in 15/16 to availability. As some of the University Seminar Site pilot is taken forward, then it is likely that that and the Athena SWAN implementation project would take up the Ring-Fenced allocation. Other work may be done where supplementary funding is agreed.

  • Athena SWAN - Payroll have suspended their project Automation of Maternity and Paternity Pay Calculations, which was expected to include the additional data fields needed for maternity for Athena SWAN. These issues are noted in PPP001 (login required), under which code the Athena SWAN analysis is being undertaken. It is currently believed that it will be possible to progress the Athena SWAN component, however this will still need some input from HR and changes to the Oracle application. If HR are able to undertake the work needed then this will be estimated and the project will go ahead in this year, subject to agreement with Payroll and Schools. This is the highest priority for SCE in 15/16 and so is included as a separate project, with the estimate currently standing at 40d for IS Applications.
  • Biological Sciences - have raised a request to support Biosciences Service and Data Hosting via IS Research Services. This would involve enabling an export of metadata records to PURE, and documenting the issues arising in linking metadata records, data files and open access publications. The action is currently with Biology to confirm if funding can be released for a short 10d technical investigation into the feasibility of what is possible, and if there are options. Note: Programme Owner has agreed that 10d could be released for this if it can be done in 10d and there is no expectation of any future funding from this allocation.
  • APIs - there is an interest in developing APIs to centrally held data, if there is a good benefit case for this then work could be undertaken in 15/16. There is a potential to supplement the funding of an Innovation Fund proposal by the remaining 6d (green circle in resources table above), which is currently being investigated.

 

Section Three: Projects in Progress

Project InfoProject Managers Commentary

SCE007 - Digitising Scotland Planning Category: Discretionary

Milestones

Please see SCE007 Milestones for details (Access to this proejct is restricted to view by IS Applications, SCE007 and CSCE Teams)

RAG Status

AMBER

Report by Sheila Fraser for November 2015
 
Please see Project Report for November for details (Access to this project is restricted to view by IS Applications, SCE007 and CSCE Teams)

SCE008 - University Seminar Site Enhancements Category: Discretionary

Milestones

10-Dec-2015Delivery
17-Dec-2015Closure
 

RAG Status

GREEN

Report by Morna Findlay for November 2015

Achievements this period

  • Build Review Approved
  • User acceptance testing completed and signed off by sponsor
  • Acceptance Review Approved
  • New Delivery milestone (10/12/15) approved

Issues

Next Steps

  • Deliver
  • Close

SCE009 - Virtual Edinburgh Scoping Category: Discretionary

Milestones

18-Dec-2015Complete evaluation and agree use case for Stage 2
18-Jan-2016Deliver Recommendation
25-Jan-2016Close

RAG Status

GREEN

Report by Morna Findlay for November 2015

Achievements in Last Period

  • Project brief approved and end of planning achieved
  • Workshops to share IS APPS and EDINA expertise arranged
  • Regular team meetings arranged
  • IS APPS resources secured

Issues

  • None

Next Steps

  • Complete technical evaluation phase

Section Four: Closed or Withdrawn Projects

Project InfoProject Managers Commentary

SCE005 - Virtual Edinburgh Business Case Support

Category: Discretionary

Report by Sheila Fraser

This project was closed on 11-Sep-15.

Please see the Completion Report for further information.

 