MVM Programme Report for Portfolio Owner Paul Clark
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Overall Programme RAG: GREEN
The MVM programme continues at a time of significant change for MVM IT. The new LTW division is now in place, with resulting changes in MVM support, and the College is undertaking a strategic review of its IT services.
With the MVM002 project now re-started and re-planned the budget situation is clearer and the programme can expect this project to deliver most of the migration in this year.
This leaves around 40 days on hand for contingency for MVM002 and to use for some key analysis/project management pieces identified by the programme owner.
MVM003 is a separate 'non-Apps' analysis piece. MVM005 is a funded development managed by the Apps Development Team - the issues around this project have also been resolved.


Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
Possible TRISTAN Replacement |
No decision taken by MVM. |
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||||||||||
MVM LTS service transition to IS Category: Funded
Milestones
RAG Status GREEN | Report completed by Maurice Franceschi for March 2015
Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||
Anatomy Museum Application Category: Core Funded
Milestones
RAG Status GREEN | Report completed by Maurice Franceschi for March 2015Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||
| MVM005 (AP45-905)
Simulated Patients Enhancements Category: Funded
Milestones
RAG Status GREEN | Report completed by Dave Berry for March 2015
Achievements in Last PeriodWork resumed on the build and the work in progress was presented to the project sponsor to review the design. This allowed the sponsor to request some changes to the UI and workflow, in time for these changes to be incorporated into the rest of the build. The schedule for testing was revised to allow for the sponsor's unavailability due to leave and exam commitments. The meeting also discussed compensation for time spent building the previous version. It was agreed that IS Apps would write-off three days of the build so far. (See https://www.projects.ed.ac.uk/project/mvm005/issues/8 ). IssuesGreg will be leaving the University at the end of May. He will hand over responsibility for this project to Ryan. The project sponsor will endeavour to test the system before the end of May so that Greg can contribute to any rework required. IS Apps will contribute three days of effort for this handover activity free of charge. (See https://www.projects.ed.ac.uk/project/mvm005/issues/7 ). Next StepsAdd the finishing touches to the build and deliver the system to the project sponsor for testing, |
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
| MVM001 | Project Closed 31/10 |