Report for December 2019

Report Date
December 2019

Report compiled by Adam Wadee

 

Section One: Programme Commentary, RAG and Resources Update

 

Section Two: Projects Not Started

 

Project Info Programme Manager's Commentary

 

All planned projects have now started.

 

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

ISG009

Alma Library Management Platform 2-Way Feed with E-Financials

Milestones

RAG Status

Project currently suspended

 

 

ISG015

IS Student Recruitment Solution

Milestones

Execute Branch Manager Recruitment 20-Jan-2020
Build Training Complete 24-Feb-2020
Design UoE / Unitemp Web Page Development 02-Mar-2020
Design Success Criteria identified for Pilot Service 02-Mar-2020
Accept Location Deployment 06-Mar-2020
Accept Web Page - Sign Off 06-Mar-2020
Accept Process - UAT 20-Mar-2020
Accept Process - Sign Off 24-Mar-2020
Execute Service Communication and Marketing Plan Roll Out 25-Mar-2020
Deliver Service Launch / Deployment - Soft 30-Mar-2020
Deliver Service Launch / Deployment - Full 06-Apr-2020
Deliver Deployment Sign Off 13-Apr-2020
Close Project Closure 20-Apr-2020

 

RAG Status

AMBER

Report by Emma McNab for December 2019

Achievements in Last Period

  • Collecting applications and shortlisting applicants to Branch Manager role

  • Interviews for the Branch Manager role

Issues 

  • Resource across project and availability of Project Sponsor
  • Reaching agreement on scope for Payroll within new service
  • Reaching agreement on nature of the Administrator role

These have been escalated to Project Sponsor / CIO

Next Steps 

Priorities include:

  • Confirm and progress preferred payroll process
  • Progress  / sign off marketing / communication templates
  • Progress plans for office location
  • Progress sign off for terms and conditions
  • Complete Branch Manager recruitment
  • Commence Administrator recruitment

 

 

 

ISG018

IT and Library Business Service Readiness for Start of Term 20/21

Milestones

Planning 10-Feb-2020
Delivery Date 12-Sep-2020
Close Date 20-Nov-2020

RAG Status

GREEN

Report by Tim Gray for December 2019

Achievements in Last Period

  • Project started

Issues

  • None

Next Steps 

  • Complete planning phase and sign off project brief.

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary

ISG016

Identity and Access Management (IDAM) Strategy

Project Closed in January 2020

ISG017

IT and Library Business Service Readiness for Start of Term 2019/20

Project Closed in December 2019

 

AttachmentSize
Image icon isg-rag-dec-19.jpg57.64 KB
Image icon isg-resources-dec-19.jpg136.53 KB
Programme Status
RAG Status
Overall
GREEN
Has formal escalation taken place?
No

Documentation