Report for November 2019

Report Date
November 2019

Report compiled by Adam Wadee

 

Section One: Programme Commentary, RAG and Resources Update

 

Section Two: Projects Not Started

 

Project Info Programme Manager's Commentary

 

All planned projects have now started.

 

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

ISG009

Alma Library Management Platform 2-Way Feed with E-Financials

Milestones

RAG Status

Project currently suspended

 

 

ISG015

IS Student Recruitment Solution

Milestones

End of Planning 22-Feb-2019
Franchise Agreement Signed 22-Feb-2019
Engagement and Communication with Stakeholders 22-Mar-2019
Service Communication and Marketing Plan Roll Out 22-Nov-2019
Locations Confirmed 09-Dec-2019
Success Criteria identified for Pilot Service 16-Dec-2019
UoE / Unitemp Web Page Development 17-Jan-2020
Location Deployment 17-Jan-2020
Web Page - Sign Off 17-Jan-2020
Branch Manager Recruitment 20-Jan-2020
Process - UAT 21-Jan-2020
Process - Sign Off 24-Jan-2020
Training Complete 27-Jan-2020
Service Launch / Deployment - Full 28-Jan-2020
Service Launch / Deployment - Soft 28-Jan-2020
Deployment Sign Off 07-Feb-2020
Project Closure 14-Feb-2020

 

RAG Status

RED

Report by Emma McNab for November 2019

Achievements in Last Period

  • Approval of PRAF / Recruitment of Branch Manager and advertising of role

  • Recruitment of p/t student to support project delivery

Issues 

  • Resource across project and availability of Project Sponsor
  • Reaching agreement on scope for Payroll within new service
  • Delayed recruitment of Branch Manager 

These have been escalated to Project Sponsor / CIO

Next Steps 

Priorities include:

  • Confirm and progress preferred payroll process
  • Progress  / sign off marketing / communication templates
  • Progress plans for office location
  • Progress sign off for terms and conditions

 

 

 

ISG016

Identity and Access Management (IDAM) Strategy

Milestones

Closure 20-Dec-2019

RAG Status

GREEN

 

Report by Adam Wadee for November 2019

Achievements this period

  • The PwC report on multi factor authentication has now been completed and signed off by the sponsor.
  • The project is now in the closure phase.

Issues

  • Closure milestone moved out to the end of December to allow the closure review to be completed.

Next steps

  • Project closure review and document the outcomes and next steps.
  • Close project.

 

 

ISG017

IT and Library Business Service Readiness for Start of Term 2019/20

Milestones

Project Closure 13-Dec-2019

RAG Status

GREEN

Report by Tim Gray for October 2019

Achievements in Last Period

Achievements in Last Period

  • Closure report drafted and circulated to key stakeholders

Issues

  • Closure has been delayed due to the PM's availability

Next Steps 

  • Review feedback to closure report
  • Close project

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary

ISG006

Establishing GDPR Support Resources

Project Closed in August 2018

ISG010

MyEd Database Upgrade

Project Closed in August 2018

ISG012

Digitisation (Library) Process Analysis

Project Closed in September 2018

ISG014

IT & Library Readiness for Start of Year 18/19

Project Closed in November 2018

ISG011

IS Apps Procurement Question Sets

Project Closed in January 2019
AttachmentSize
Image icon isg-rag-nov-19.jpg46.74 KB
Image icon isg-resources-nov-19.jpg129.44 KB
Programme Status
RAG Status
Overall
GREEN
Has formal escalation taken place?
No

Documentation

Not available.