Report for July 2019

Report Date
July 2019

Report compiled by Adam Wadee

 

Section One: Programme Commentary, RAG and Resources Update

 

 

Section Two: Projects Not Started

 

Project Info Programme Manager's Commentary

 

All planned projects have now started.

 

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

ISG009

Alma Library Management Platform 2-Way Feed with E-Financials

Milestones

RAG Status

Project currently suspended until May 2019

 

 

ISG015

IS Student Recruitment Solution

Milestones

Success Criteria identified for Pilot Service

16-Aug-2019

Branch Manager Recruitment

30-Aug-2019

Locations Confirmed

30-Aug-2019

Service Communication and Marketing Plan Roll Out

31-Oct-2019

UoE / Unitemp Web Page Development

15-Nov-2019

Training Complete

29-Nov-2019

Location Deployment

29-Nov-2019

Web Page - Sign Off

29-Nov-2019

Process - UAT

29-Nov-2019

Process - Sign Off

03-Dec-2019

Service Launch / Deployment - Soft

05-Dec-2019

Service Launch / Deployment - Full

20-Jan-2020

Deployment Sign Off

31-Jan-2020

Project Closure

07-Feb-2020

 

RAG Status

GREEN

Report by Emma McNab for July 2019

Achievements in Last Period

  • Further Kick Off Sessions with Unitemps

  • Draft JD for Branch Manager

  • Brief for Focus Groups

  • EqIA drafted

Issues 

  • n/a

Next Steps 

  • Finalise Communication Plan
  • Consultation and engagement - survey and focus groups for baseline data
  • To Be mapping

ISG016

Identity and Access Management (IDAM) Strategy

Milestones

Deliver Phase 5: Assess immediate operational impact and longer term strategic implications of Multi-Factor Authentication (MFA) 30-Aug-2019
Close Create closure report 06-Sep-2019

RAG Status

GREEN

 

Report by Paul De'Ath for July 2019

Achievements this period

  • Alistair published thanks and a summary document to all those involved in the project
  • A new scope addition was approved and PwC met the key UoE colleagues involved - multi factor authentication
  • Draft close report commenced

Issues

  • N/A

Next steps

  • PwC to deliver the document in August
  • Close milestone needs to move out to late August/early September

 

 

ISG017

IT and Library Business Service Readiness for Start of Term 2019/20

Milestones

Staff Contact Lists for Start of Term Agreed 26-Jul-2019
Welcome Week Planning Complete 09-Aug-2019
Start of Welcome Week (External Milestone) 09-Sep-2019
Start of Teaching Week 1 (External Milestone) 16-Sep-2019
Start of Teaching Week 2 (External Milestone) 23-Sep-2019
Delivery Sign Off Review following Start of Session 14-Oct-2019
Project Closure 15-Nov-2019

RAG Status

GREEN

Report by Tim Gray for July 2019

Achievements in Last Period

  • Welcome Week planning continues to progress as planned;
    • planning for Principal's visit on 9th September 2019 progressing well
    • POs raised for queue management
    • floor plan for week 0 and weeks 1 & 2 reviewed
    • Posters and digital assets in progress
    • comms for Library staff drafted
    • webpages under review
  • Bi-weekly Meetings continue as planned with updates to the Wiki pages made on an on-going basis.
    • No red projects
    • 6 AMBER projects
    • 3 AMBER user-facing applications
    • 1 AMBER supporting application

Issues

  • No issues to report

Next Steps 

  • Continue with Welcome Week planning in all areas
    • recruitment student helpers
    • finalise Principal's visit
    • update webpages after review
    • confirm wording changes to student email comms
    • progress other areas of planning
  • Continue with weekly project meetings

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary

ISG006

Establishing GDPR Support Resources

Project Closed in August 2018

ISG010

MyEd Database Upgrade

Project Closed in August 2018

ISG012

Digitisation (Library) Process Analysis

Project Closed in September 2018

ISG014

IT & Library Readiness for Start of Year 18/19

Project Closed in November 2018

ISG011

IS Apps Procurement Question Sets

Project Closed in January 2019

 

AttachmentSize
Image icon isg-rag-jul-19.jpg62.79 KB
Image icon isg-resources-jul-19.jpg163.84 KB

Documentation