Report for March 2019

Report Date
March 2019

Report compiled by Adam Wadee

 

Section One: Programme Commentary, RAG and Resources Update

 

 

 

 

Section Two: Projects Not Started

 

Project Info Programme Manager's Commentary

 

All planned projects have now started.

 

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

ISG009

Alma Library Management Platform 2-Way Feed with E-Financials

Milestones

RAG Status

Project currently suspended until May 2019

 

 

ISG015

IS Student Recruitment Solution

Milestones

Delivery Date - 21-June-2019

Close Date - 19-jul -2019

RAG Status

GREEN

Report by Emma McNab for March 2019

Achievements in Last Period

  • Engagement with stakeholders

  • Draft Communication Plan

Issues 

  • Ongoing delay in progressing sign off of Franchise Agreement may result in project milestones being pushed out and increases risks aligned to budget.  Actions are being deployed to progress the deployment and will be escalated if appropriate.

Next Steps 

  • Franchise Agreement Sign Off
  • Engagement with wider Stakeholders

 

 

ISG016

Identity and Access Management (IDAM) Strategy

Milestones

Initiate Commence project with agreed budget complete
Plan Project brief approval complete
Analyse Phase 1 - understand the 'as is' environment complete
Design Phase 2: define the strategy, architecture and operating model 12-Apr-2019
Build Phase 3: establish the roadmap 26-Apr-2019
Deliver Phase 4: support establishment of a business plan 10-May-2019
Close Create closure report 07-Jun-2019

RAG Status

GREEN

 

Report by Paul De'Ath for March 2019

Achievements this period

  • PWC delivered 'as is' and it was approved by sponsor and key stakeholders
  • PWC approval confirmed to continue with target state etc

Issues

  • PWC reporting slightly behind original schedule, but the sponsor and key stakeholders are comfortable
  • Slight delay with payment to PWC, finance ticket raised

Next steps

  • Continue to support PWC and sponsor requirements
  • Deliver update to WIS

 

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary

ISG006

Establishing GDPR Support Resources

Project Closed in August 2018

ISG010

MyEd Database Upgrade

Project Closed in August 2018

ISG012

Digitisation (Library) Process Analysis

Project Closed in September 2018

ISG014

IT & Library Readiness for Start of Year 18/19

Project Closed in November 2018

ISG011

IS Apps Procurement Question Sets

Project Closed in January 2019

 