Report for January 2019

Report Date
January 2019

Report compiled by Adam Wadee

 

Section One: Programme Commentary, RAG and Resources Update

 

 

 

Section Two: Projects Not Started

 

Project Info Programme Manager's Commentary

 

All planned projects have now started.

 

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

ISG009

Alma Library Management Platform 2-Way Feed with E-Financials

Milestones

RAG Status

Project currently suspended until May 2019

 

 

ISG015

IS Student Recruitment Solution

Milestones

 

Start Date - 04-Oct-2018

Planning Date - 11-Jan-2019

Delivery Date - 31-May-2019

Close Date - 28-Jun-2019

RAG Status

GREEN

Report by Emma McNab for January 2019

Achievements in Last Period

  • Project initiation

  • Brief drafted

  • Engagement with stakeholders

  • Contract approval

Issues 

  • Slight delay in progressing discussions with supplier and finalising contract however this is within tolerance.

 

Next Steps 

  • Brief sign off / end of planning

 

ISG016

Identity and Access Management (IDAM) Strategy

Milestones

Initiate Commence project with agreed budget 25-Jan-2019
Plan Project brief approval 30-Jan-2019
Analyse Phase 1 - understand the 'as is' environment 08-Mar-2019
Design Phase 2: define the strategy, architecture and operating model 12-Apr-2019
Build Phase 3: establish the roadmap 26-Apr-2019
Deliver Phase 4: support establishment of a business plan 10-May-2019
Close Create closure report 07-Jun-2019

RAG Status

GREEN

 

Report by Paul De'Eath for January 2019

Achievements this period

  • Project initiated and brief created and approved by Sponsor - WIS have some comments
  • Attended IDM user group
  • Schedule a series of meetings with PWC around understanding 'as is'

Issues

  • Basic risks added to register

Next steps

  • Develop further meetings for PWC, chase actions, assist in weekly reporting
  • Meet Adam and Mark to review WIS comments

 

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary

ISG006

Establishing GDPR Support Resources

Project Closed in August 2018

ISG010

MyEd Database Upgrade

Project Closed in August 2018

ISG012

Digitisation (Library) Process Analysis

Project Closed in September 2018

ISG014

IT & Library Readiness for Start of Year 18/19

Project Closed in November 2018

ISG011

IS Apps Procurement Question Sets

Project Closed in January 2019

 