Report for December 2018

Report Date
December 2018

Report compiled by Adam Wadee

 

Section One: Programme Commentary, RAG and Resources Update

 

 

Section Two: Projects Not Started

 

Project Info Programme Manager's Commentary

 

All planned projects have now started.

 

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

ISG009

Alma Library Management Platform 2-Way Feed with E-Financials

Milestones

TBC

Delivery
TBC Closure

 

RAG Status

Issue: AMBER: Delay in the final draft of the Business Analysis report being created due to Business Analyst leaving the business along with a resource conflict for the Project Manager.

Report by Lee-Ann Simpson for December 2018

Achievements

 

No work was undertaken on ISG009 in December due to the PM being unavailable as a result of a major corporate deployment.

 

Issues 

 

  • Business Analyst left the business which impacted upon the completion of the report.
  • Project Manager time required to be conflicted due to additional time required on a Priority One project.

 

Next Steps 

 

  • Business Analysis report to be completed and passed out for review;
  • Milestones to be reviewed and amended;
  • Closure report to be completed;
  • Project to be closed.

 

 

ISG011

IS Apps Procurement Question Set

Milestones

Target Date Title
15-Dec-2018 Question Set Checkpoint 1 (after 4th question set review)
15-Dec-2018 Question Set Checkpoint 2 (after 8th question set review
De-Scoped Question Set Governance
16-Jan-2019 Completion of the Procurement Question Set Review
23-Jan-2019 Closure

RAG Status

AMBER: Due to the change due to be submitted to WIS on the 10th January, this project is now on tracking as Amber until approval has been gained to move the milestones to cover the remaining work required to complete the project.

Report by Lee-Ann Simpson for December 2018

Achievements

  • All question sets (with the exception of 'Training & Implementation' and 'Product Roadmap' were signed off in November and re-formatted for consistency;
  • Weighting calculations amended to account for the inclusion of an 'absolute weighting' to support Procurement;
  • Scope of the project amended and signed off via WIS to remove the following:
    • Training & Implementation Question Set;
    • Product Roadmap Question Set;
    • Embedded PMO Governance.
  • Project re-planned to account for the above requirements being de-scoped.
  • Procurement confirmed that they believed the Wiki page would be OK to house the Procurement Question Sets.

Issues 

  • Securing resource availability for the key stakeholders in order to complete the outstanding tasks proved to be an issue which resulted in the overall time scales and budget of the project being extended and ultimately resulted in requirements being de-scoped.
  • PMO were unable to provide resource to support in the PMO governance requirement which resulted in this being de-scoped.

Next Steps

  • 'Training & Implementation' and 'Product Roadmap' owner to confirm which working version of both question sets should be used.  Once confirmed, these will require to be reformatted in line with all other question sets.
  • Delivery and Closure milestones to be amended (to allow for the final review by Procurement) and passed via WIS.
  • Delivery of the question sets.
  • Closure report to be completed.
  • Project to be closed.

ISG015

IS Student Recruitment Solution

Milestones

 

Start Date - 04-Oct-2018

Planning Date - 11-Jan-2019

Delivery Date - 31-May-2019

Close Date - 28-Jun-2019

RAG Status

GREEN

Report by Emma McNab
December 2018

Achievements in Last Period

  • Project initiation

  • Brief drafted

  • Engagement with stakeholders

  • Contract approval

Issues 

  • Slight delay in progressing discussions with supplier and finalising contract however this is within tolerance.

 

Next Steps 

  • Brief sign off / end of planning

 

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary

ISG006

Establishing GDPR Support Resources

Project Closed in August 2018

ISG010

MyEd Database Upgrade

Project Closed in August 2018

ISG012

Digitisation (Library) Process Analysis

Project Closed in September 2018

ISG014

IT & Library Readiness for Start of Year 18/19

Project Closed in November 2018

 

AttachmentSize
Image icon isg-rag-jan-19.jpg60.55 KB
Image icon isg-resources-jan-19.jpg133.44 KB