Report for November 2018
- Report Date
- November 2018
Report compiled by Adam Wadee
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update


| Project Info | Programme Manager's Commentary |
|
|
All planned projects have now started. |
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||||||
|
ISG009 Alma Library Management Platform 2-Way Feed with E-Financials Milestones
RAG Status Issue: AMBER: Delay in the final draft of the Business Analysis report being created due to Business Analyst leaving the business along with a resource conflict for the Project Manager. |
Report by Lee-Ann Simpson for October 2018 Achievements
No work was undertaken on ISG009 in November due to the PM being unavailable as a result of a major corporate deployment.
Issues
Next Steps
|
||||||||||||
|
ISG011 IS Apps Procurement Question Set Milestones
RAG Status AMBER: Due to challenges with stakeholder availability, a request to amend the milestones and overall budget will be submitted to WIS on 7th December 2018. Above Milestones show the current signed off and agreed dates....subject to change on Friday. |
Report by Lee-Ann Simpson for October 2018 Achievements
Issues
Next Steps
|
||||||||||||
|
ISG015 IS Student Recruitment Solution Milestones Start Date - 04-Oct-2018 Planning Date - 16-Nov-2018 Delivery Date - 31-May-2019 Close Date - 28-Jun-2019 RAG Status GREEN |
Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
|
ISG006 Establishing GDPR Support Resources |
Project Closed in August 2018 |
|
ISG010 MyEd Database Upgrade |
Project Closed in August 2018 |
|
ISG012 Digitisation (Library) Process Analysis |
Project Closed in September 2018 |
|
ISG014 IT & Library Readiness for Start of Year 18/19 |
Project Closed in November 2018 |