- Report Date
- October 2018
Report compiled by Adam Wadee
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update


| Project Info |
Programme Manager's Commentary |
|
|
All planned projects have now started. |
Section Three: Projects in Progress
| Project Info |
Project Managers Commentary |
|
ISG009
Alma Library Management Platform 2-Way Feed with E-Financials
Milestones
RAG Status
Amber: Issue: Delay in the final draft of the Business Analysis report being created due to Business Analyst leaving the business along with a resource conflict for the Project Manager.
|
Report by Lee-Ann Simpson for October 2018
Achievements
- Additional feedback on the business analysis report provided to business analysis.
Issues
- Business Analyst left the business which impacted upon the completion of the report.
- Project Manager time required to be conflicted due to additional time required on a Priority One project.
Next Steps
- Business Analysis report to be completed and passed out for review;
- Milestones to be reviewed and amended;
- Closure report to be completed;
- Project to be closed.
|
|
ISG011
IS Apps Procurement Question Set
Milestones
RAG Status
GREEN: Due to challenges with stakeholder availability, a request to amend the milestones and overall budget was approved on the 16th October. Project is now on track.
|
Report by Lee-Ann Simpson for October 2018
Achievements
- All question sets with the exception of ‘Implementation & Training’ along with the ‘Product Roadmap’ have been signed off by Head of Project Services, Head of Production Management, Head of Development Services and Head of Service Management.
- Initial review of ‘Implementation & Training’ along with the ‘Product Roadmap’ was completed and was passed out for review to all stakeholders.
- Procurement question sets were re-formatted to improve consistency across all question sets.
- Agreement on key terminology was agreed with the stakeholder population.
Issues
- Securing resource availability for the key stakeholders in order to complete the outstanding tasks proved to be an issue which resulted in the overall timescales and budget of the project being extended.
Next Steps
- Obtain first draft of the PMO documentation circulate for review prior to final version being created (or pass this across to be picked up via an alternative project).
- Final review of all question sets in line with the team meeting held on 1st November to align the guidance, questions and governance to create a better end user experience.
- Support documentation to be created for the question sets to complement the Contextual Metrics and Dimensions document to be created, reviewed and signed off by the project team.
- A location for the question sets to permanently be located to be agreed to ensure wider access across the University.
- Closure report to be completed.
- Project to be closed.
|
|
ISG014
IT & Library Readiness for Start of Year 18/19
Milestones
RAG Status
AMBER
|
Report by Colin Watt for October 2018
Achievements in last period
- Lessons Learned report in progress incorporating feedback from sessions with IS and Estates stakeholders.
- Meeting with estates; some actions agreed to include IS in loop re: lookahead of major projects for the next year.
Issues
- No major issues.
- Delay to project closure due to availability of Project Sponsor, PM, and Estates staff.
Next Steps
- Complete Lessons Learned report with input from key stakeholders - coordinated by Project Sponsor and PM.
- Project Closure.
The project RAG status is currently AMBER, due to delay in closure.
|
|
ISG015
IS Student Recruitment Solution
Milestones
-
Start Date - 04-Oct-2018
Planning Date - 16-Nov-2018
Delivery Date - 31-May-2019
Close Date - 28-Jun-2019
RAG Status
GREEN
|
- Report by Emma McNab for October 2018
Achievements in Last Period
- Initiation Meeting
- Initial Meeting with Franchise representative
- Brief drafted
Issues
Next Steps
- Brief sign off / end of planning
- Project initiation
|
Section Four: Closed or Withdrawn Projects
| Project Info |
Project Managers Commentary |
|
ISG006
Establishing GDPR Support Resources
|
Project Closed in August 2018 |
|
ISG010
MyEd Database Upgrade
|
Project Closed in August 2018 |
|
ISG012
Digitisation (Library) Process Analysis
|
Project Closed in September 2018 |