Report for September 2018

Report Date
September 2018

Report compiled by Adam Wadee

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

 

 

 

Project Info Programme Manager's Commentary

 

All planned projects have now started.

 

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

ISG009

Alma Library Management Platform 2-Way Feed with E-Financials

Milestones

TBC

Delivery
TBC Closure

 

RAG Status

Amber: Issue: Delay in the final draft of the Business Analysis report being created due to leave within the team

Report by Lee-Ann Simpson for September 2018

 

Achievements

 

  • First draft of the Business Analysis report reviewed with feedback provided.

 

Issues 

 

  • Delay in the final draft of the Business Analysis report being created due to leave within the team.
  • Milestones not amended due to A/L - agreement to change milestones to be gained and progressed.

 

Next Steps 

 

  • Complete the final Business Analysis report and share with the project team for approval.
  • Complete Closure Report.
  • Close Project

 

 

ISG011

IS Apps Procurement Question Set

Milestones

Target Date Title
28-Sep-2018 Question Set Checkpoint 1 (after 4th question set review)
28-Sep-2018 Question Set Checkpoint 2 (after 8th question set review
12-Oct-2018 Question Set Governance
12-Oct-2018 Completion of the Procurement Question Set Review
26-Oct-2018 Closure

RAG Status

AMBER: Issue: Issue: Due to challenges with stakeholder availability, Check point # 1 and 2 were due to be completed by 28th September; however, this is still in progress.

Report by Lee-Ann Simpson for September 2018

Achievements

  • Final push on remainder of the question sets undertaken to allow the project to move to the final stages before closure.

Issues 

  • Neither question milestones (check point # 1 and checkpoint # 2) have been signed off as of yet due to the requested changes.
  • PMO guidance milestone has been slipped into October due to Annual Leave within the team.
  • Implementation and Training and Product Development question sets have not yet been reviewed.
  • Project Manager A/L within September.

Next Steps 

  • Obtain first draft of the PMO documentation circulate for review prior to final version being created (or pass this across to be picked up via an alternative project).
  • Proposal created to consolidate the current question sets further to be reviewed and signed off/closed with subsequent actions to be picked up and completed.
  • Reviewed remainder of the question sets and prepared for sign off;
  • Format of the all procurement questions to be re-created once the final sign off has been completed along with providing both the absolute and relative % weightings.

 

ISG014

IT & Library Readiness for Start of Year 18/19

Milestones

12-Oct-2018 Delivery Sign Off Review following Start of Session
26-Oct-2018 Project Closure

 

RAG Status

GREEN

Report by Colin Watt for September 2018

Achievements in last period

 

Issues

  • No major issues.

 

Next Steps

  • Complete Lessons Learned report with input from key stakeholders - coordinated by Project Sponsor and PM.
  • Project Closure.

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary

ISG006

Establishing GDPR Support Resources

Project Closed in August 2018

ISG010

MyEd Database Upgrade

Project Closed in August 2018

ISG012

Digitisation (Library) Process Analysis

Project Closed in September 2018

 

AttachmentSize
Image icon isg-resources-sep-18.jpg119.16 KB

Documentation

Not available.