Report for August 2018

Report Date
August 2018

Report compiled by Adam Wadee

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

 

 

 

Project Info Programme Manager's Commentary

 

All planned projects have now started.

 

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

ISG009

Alma Library Management Platform 2-Way Feed with E-Financials

Milestones

07-Sep-2018

Delivery
28-Sep-2018 Closure

 

RAG Status

Amber: Issue: Delay in the final draft of the Business Analysis report being created due to leave within the team

Report by Lee-Ann Simpson for August 2018

 

Achievements

 

  • First draft of the Business Analysis report being created.

 

Issues 

 

  • Delay in the final draft of the Business Analysis report being created due to leave within the team.

 

Next Steps 

 

  • Complete the final Business Analysis report and share with the project team for approval.
  • Complete Closure Report.
  • Close Project

 

 

ISG011

IS Apps Procurement Question Set

Milestones

Target Date Title
28-Sep-2018 Question Set Checkpoint 1 (after 4th question set review)
28-Sep-2018 Question Set Checkpoint 2 (after 8th question set review
12-Oct-2018 Question Set Governance
12-Oct-2018 Completion of the Procurement Question Set Review
26-Oct-2018 Closure

RAG Status

AMBER: Issue: Due to challenges with stakeholder availability, all milestones have slipped as a result.

Report by Lee-Ann Simpson for August 2018

Achievements

  • Checkpoint # 1 reviewed by Service Management and feedback provided.  No sign off has been gained due to the feedback provided.
  • Checkpoint # 2 reviewed by the Head of Project Services and feedback provided.  No sign off has been gained due to the feedback provided.
  • Discussions held with question set owners of ‘Usability’, ‘On Prem’, ‘Mandatory’ and ‘SLA’ with feedback provided – actions have been taken away from each conversation to be completed before sign off can be provided.
  • Checkpoint # 2 sent out for review and sign off.
  • Meeting held with procurement to gather feedback on changes to the procurement question sets and gain support to the direction the question sets are following
  • A proposal has been created and circulated due to feedback received by Service Management in which question contained within the question sets are to be reduced further by consolidating current questions which, in turn, will support in more accurate scoring of the question sets.

Issues 

  • Project dates slipped again with the new, amended close date moving to Mid-October.
  • An additional 2 days budget had to be requested to cover the project management due to the slippage.
  • Neither question milestones (check point # 1 and checkpoint # 2) have been signed off as of yet due to the requested changes.
  • PMO guidance milestone has been slipped into October due to Annual Leave within the team.
  • Implementation and Training and Product Development question sets have not yet been reviewed

Next Steps 

  • Obtain first draft of the PMO documentation circulate for review prior to final version being created (or pass this across to be picked up via an alternative project).
  • Proposal created to consolidate the current question sets further to be reviewed and signed off/closed with subsequent actions to be picked up and completed.
  • Reviewed remainder of the question sets and prepared for sign off (with exception of: Implementation and Training and Product Development);
  • Format of the all procurement questions to be re-created once the final sign off has been completed along with providing both the absolute and relative % weightings.

 

ISG012

Digitisation (Library) Process Analysis

Milestones

7-Sep-2018

Closure

 

RAG Status

GREEN

Report by Sue Woodger for August 2018

Achievements in Last period

  • As-is interviews completed
  • Delivery: Business analysis sign off: Recommendations and high level requirements presented to Kirsty Lingstadt, Joe Marshall, Norman Roger and Karen Stirling. All were happy with the report and will be meeting to discuss how they can take the first 3 points forward and disseminate to Library staff
    • Point 1 was to Digitise your processes
    • Point 2 was to Streamline your systems
    • Point 3 was to Improve metadata and catalogues
    • Point 4 Promote yourselves requires wider university website integration
    • Point 5 Enhance the student experience is for the future – points 1-3 need to be happen first

 

Issues

  • Higher priority project commitments, end of year and sheer volume of write ups meant that PM has been unable to complete the as-is write ups

Next Steps

  • Complete as-is write ups
  • Close

 

RAG Commentary: N/A - Project is GREEN

ISG014

IT & Library Readiness for Start of Year 18/19

Milestones

04-Sep-2018 Start of Welcome Week (External Milestone)
17-Sep-2018 Start of Teaching Week 1 (External Milestone)
24-Sep-2018 Start of Teaching Week 2 (External Milestone)
12-Oct-2018 Delivery Sign Off Review following Start of Session
26-Oct-2018 Project Closure

 

RAG Status

GREEN

Report by Colin Watt for August 2018

Achievements in last period

  • Communications Plan milestone achieved.
  • Agreed Staff Contact Lists milestone achieved.
  • Final updates to Readiness wiki page to be completed ahead of SMT meeting 04/09/18.
  • Final regular project team meeting scheduled for 05/09/18 where the expectation is that the Start of Welcome Week (External Milestone) milestone be recorded as achieved
  • The Readiness wiki page indicates an overall positive position ahead of start of session, with some additional lessons from this project to be learned for start of session preparation in future years.

 

Issues

  • No major issues.

 

Next Steps

The project RAG status is currently GREEN.

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary

ISG006

Establishing GDPR Support Resources

Project Closed in August 2018

ISG010

MyEd Database Upgrade

Project Closed in August 2018

 

AttachmentSize
Image icon isg-rag-aug-18.jpg45.36 KB
Image icon isg-resources-aug-18.jpg120.39 KB

Documentation

Not available.