Report for July 2018
- Report Date
- July 2018
Report compiled by Adam Wadee
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update


| Project Info | Programme Manager's Commentary |
|
|
All planned projects have now started. |
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||||||||||||||
|
ISG006 Establish GDPR Support Resources
Milestones Project is now closed RAG Status BLUE
|
Report by David Watters for July 2018 Achievements
Issues
Next steps
|
||||||||||||||||||||
|
ISG009 Alma Library Management Platform 2-Way Feed with E-Financials Milestones
RAG Status Amber: Issue: Project sitting at Amber status due to Business Analysis milestone having to slip to accommodate A/L for business users. |
Report by Lee-Ann Simpson for July 2018 Achievements
Issues
Next Steps
|
||||||||||||||||||||
|
ISG010 MyEd Database Migration to Oracle 12 Milestones
RAG Status GREEN
|
Report by Richard Bailey for June 2018 Achievements in last period
Issues
Next Steps
|
||||||||||||||||||||
|
ISG011 IS Apps Procurement Question Set Milestones RAG Status AMBER: Issue: Due to challenges with stakeholder availability, some milestones have slipped as a result. |
Report by Lee-Ann Simpson for July 2018 Achievements
Issues
Next Steps
|
||||||||||||||||||||
|
ISG012 Digitisation (Library) Process Analysis Milestones
RAG Status GREEN |
Report by Sue Woodger for July 2018 Achievements in last period
Issues
Next Steps
RAG Commentary: N/A - Project is GREEN as revised milestones have been approved |
||||||||||||||||||||
|
ISG014 IT & Library Readiness for Start of Year 18/19 Milestones
RAG Status AMBER |
Report by Colin Watt June 2018 Achievements in last period
Issues
Next Steps
The project RAG status is currently AMBER (time) due to the Agreed IS Staff Involvement milestone not yet being achieved; (Project Sponsor and PM awaiting confirmation of representative from L&UC); Communications Plan milestone delayed due to USD staff availability. Expect status to return to GREEN next month. |
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
|
ISG003 Projects Website Migration Category: Compliance |
Project Closed on 12 May 2017. |
|
ISG005 Monitoring IT and Library Business Service Readiness For Start of Term 2017/18 |
Project Closed on 3 November 2017 |
|
ISG007 Architecture Repository Implementation |
Project Closed on 3 November 2017 |