Report for May 2018
- Report Date
- May 2018
Report compiled by Adam Wadee
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update

For security reasons, images aren't duplicated during cloning. Please re-add or replace the image as required.
| Project Info | Programme Manager's Commentary |
|
|
All planned projects have now started. |
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||||||||||||||||
|
ISG006 Establish GDPR Support Resources
Milestones
RAG Status GREEN
|
Report by David Watters for May 2018 Achievements
Issues
Next steps
|
||||||||||||||||||||||
|
ISG009 Alma Library Management Platform 2-Way Feed with E-Financials Milestones
RAG Status AMBER: Due to the significant delays experienced within this project, we have identified that there is a risk that this project will not be completed within the current financial year and may require additional budget in order to complete the business analysis and subsequent project management. |
Report by Lee-Ann Simpson for May 2018 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||||
|
ISG010 MyEd Database Migration to Oracle 12 Milestones
RAG Status GREEN
|
Report by Richard Bailey for May 2018 Achievements in last period
Issues
Next Steps
|
||||||||||||||||||||||
|
ISG011 IS Apps Procurement Question Set Milestones RAG Status GREEN |
Report by Lee-Ann Simpson for May 2018 Achievements1. Review of the initial questions set undertaken with sign off requested for:
2. It was discussed with the sponsor to determine whether these question sets should be used for all procurements or whether there should be an alternative process/guidance for lower cost procurements. It was agreed that:
3. It was discussed with the project sponsor the possibility of cloud based solutions and whether we would be happy for departments (out with IS) to buy any cloud based solutions without the need for input from IS or whether we would require an IS Gateway to verify any systems in question (in particular, if there were a need to integrate with an existing IS solution). It was agreed that:
Issues
Next Steps
|
||||||||||||||||||||||
|
ISG012 Digitisation (Library) Process Analysis Milestones
RAG Status AMBER |
Report by Sue Woodger for April 2018 Achievements in Last period
Issues
Next Steps
The project status is AMBER as PM has to review milestones |
||||||||||||||||||||||
|
ISG014 IT & Library Readiness for Start of Year 18/19 Milestones (subject to planning approval)
RAG Status GREEN |
Report by Colin Watt May 2018 Achievements in last period
Issues
Next Steps
The project status is GREEN
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
|
ISG003 Projects Website Migration Category: Compliance |
Project Closed on 12 May 2017. |
|
ISG005 Monitoring IT and Library Business Service Readiness For Start of Term 2017/18 |
Project Closed on 3 November 2017 |
|
ISG007 Architecture Repository Implementation |
Project Closed on 3 November 2017 |
| Attachment | Size |
|---|---|
| 84.58 KB | |
| 188.29 KB |

