Report for April 2018

Report Date
April 2018

Report compiled by Adam Wadee

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

 

For security reasons, images aren't duplicated during cloning. Please re-add or replace the image as required.

 

Project Info Programme Manager's Commentary

 

All planned projects have now started.

 

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

ISG006

Establish GDPR Support Resources

 

Milestones

09-May-2018 May progress checkpoint Deliver
01-Jun-2018 Delivery (Readiness) sign-off Deliver
21-Jun-2018 Project closure Close

RAG Status

GREEN

 

Report by David Watters for April 2018

Achievements

  • Prepared April report for readiness aspect
  • Worked with project sponsor to arrange DP Champion training
  • Implemented DP Champions mailing list and associated communications

Issues

  • Sharepoint site not yet communicated to all ISG staff

Next steps

  • Distribute Sharepoint site to ISG staff
  • Prepare May report for readiness aspect and forward to CISO for reporting to SMT

 

 

 

 

 

 

ISG009

Alma Library Management Platform 2-Way Feed with E-Financials

Milestones

TBC 

Planning

TBC 

Business Analysis

TBC 

Delivery

TBC 

Closure

 

RAG Status

RED: Issue: We have identified a Finance Service Lead (Douglas Stewart) who has committed to providing availability throughout the ISG009 project; however, the risk has been left in place as Finance are currently involved in the Core Systems Procurement and the eFin upgrade (FIN118) which may further impact upon Douglas's availability.

Report by Lee-Ann Simpson for April 2018

Achievements in Last Period

  • Obtained commitment from Finance to have representation on the project which will allow this to progress before the end of the current financial year.
  • Obtained a new Project Manager - Lee-Ann Simpson.

Issues

  • There is a current potential issue regarding IS Service Development resource.  As this is a ‘Viability and Feasibility’ project, IS Service Development support will be minimal and as such, is currently being reviewed.

Next Steps

  • Complete planning for the project.
  • Project brief to be signed off.
  • Business Analysis to be commenced.

 

ISG010

MyEd Database Migration to Oracle 12

Milestones

 

30 Mar 2018   Suspend the Project
28 May 2018   Restart the Project
01-Jun-2018   Build
15-Jun-2018 Integration
13-Jul-2018 Acceptance
17-Jul-2018 Deployment
27-Jul-2018 Closure

 

 

RAG Status

BLUE - Suspended until 28th May 2018

Report by Richard Bailey for April 2018

Achievements in last period

  • The upgrade of the DEV/BETA environments were completed
  • The project, due to the impact of Industrial Action has been re-planned for a deployment date to LIVE of 17th July 2018, which is agreed with the Project Sponsor / Business as this falls in the lower risk summer post-exam period to the Students
  • The milestones have been reset and all bookings have been reconfirmed / re-planned in ASTA
  • Project Governance meetings are booked / set to recommence from 22/05/2018
  • The Project was suspended at WIS 30/03/2018
  • Channel / portal owners have been updated / temporarily stood down to conduct testing, a new window has been identified in late June / early July

Issues

  • ISSUE:  Loss of Resource due to Industrial Action - This issue has caused the project suspension.   Impact of the Industrial Action:  Development Technology days lost: 7

    Cost of the Industrial Action:  The additional project management, approval and booking of resource required to re-plan this project due to industrial action is estimated at 1.5 days

Next Steps

  • Re-start the Project / take off of suspended status 28th May 2018.

 

ISG011

IS Apps Procurement Question Set

Milestones

Target DateFor security reasons, images aren't duplicated during cloning. Please re-add or replace the image as required. Title
04-May-2018 Question Set Checkpoint 1 (after 4th question set review)
18-May-2018 Question Set Governance
15-Jun-2018 Question Set Checkpoint 2 (after 8th question set review)
20-Jul-2018 Completion of the Procurement Question Set Review
27-Jul-2018 Closure

RAG Status

GREEN

Report by Lee-Ann Simpson for April 2018

Achievements

  • Review of question sets contained within the initial milestone are currently underway:

    • Support and Maintenance
    • Implementation and Training
    • Technology
    • Technical Appendix
  • Technical question sets have been reviewed with additional time required.  Meeting originally scheduled for 20th April has been rescheduled to 1st May.

Issues

  • The project has continued to run slightly behind due to the in depth requirements of the initial set of procurement questions.  Whilst this has caused a delay to the initial milestones, it is accepted that all remaining question sets will not require the same degree of resource to review and thus will potentially allow for some time to be made back
  • Changed to the overall planned effort and one of the minor milestones observed.  This change was approved by the project team.
  • PMO Governance meeting required to review Question Set Governance as per the project plan.

Next Steps

  • Complete the review of the initial 4 questions sets and subsequent sign off:

    • Support and Maintenance
    • Implementation and Training
    • Technology
    • Technical Appendix
  • Commence with review of project methodology.
  • Discuss with project sponsor whether it is the intention to have these question sets cover all procurement activity or whether an alternative process should be considered for lower cost procurement (i.e. under £50K) – this may be out of scope for the purposes of this project.
  • Discuss with project sponsor the possibility of cloud based solutions and whether we would be happy for departments (out with IS) to buy any cloud based solutions without the need for input from IS or whether we would require an IS Gateway to verify any systems in question (in particular, if there were a need to integrate with an existing IS solution).

 

ISG012

Digitisation (Library) Process Analysis

Milestones

01-Jun-2018 Business Analysis sign off
15-Jun-2018 Delivery
20-Jun-2018 Delivery Review
29-Jun-2018 Project Closure

RAG Status

GREEN

Report by Sue Woodger for April 2018

Achievements in Last period

  • Project Brief completed and approved 12 April 18
  • Business Analysis kicked off with meetings with Claire Knowles, Norman Rodger and Joe Marshall
  • ‘Straw man’ created to kick off as-is investigations

 

 

Issues

  • None

 

Next Steps

  • Set up meetings with staff to capture the as-is

 

The project status is GREEN

ISG014

IT & Library Readiness for Start of Year 18/19

Initial Milestones

Target Datesort descending Title
01-May-2018 Start of Project
18-May-2018 Project brief and planning
17-Sep-2018 Delivery : Start of Term
12-Oct-2018 Project Closure

RAG Status

GREEN

Report by Karen Stirling April 2018

Achievements in last period

  • Project initiated
  • Project manager assigned
  • Project website created

Issues

  • None

Next Steps

  • Identify Stakeholders and Area Representatives
  • Complete project brief and planning

 

The project status is GREEN

 

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary

ISG003

Projects Website Migration

Category: Compliance

Project Closed on 12 May 2017.

ISG005

Monitoring IT and Library Business Service Readiness For Start of Term 2017/18

Project Closed on 3 November 2017

ISG007

Architecture Repository Implementation

Project Closed on 3 November 2017

 

AttachmentSize
Image icon isg-rag-apr-18v2.jpg90.24 KB
Image icon isg-resources-apr-18.jpg221.28 KB

Documentation

Not available.