Report for January 2018

Report Date
January 2018

Report compiled by Adam Wadee

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

 

Section Two: Projects Not Started

 

Project Info Programme Manager's Commentary

 

All planned projects have now started.

 

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

ISG006

Establish GDPR Support Resources

 

Milestones

15-Feb-2018 Delivery sign-off Deliver
22-Jun-2018 Project closure Close

RAG Status

RED

Issue: Deliverables have still not been signed off by project team. This has impacted on the original closure of the project and is now scheduled for mid-February. No action required by SMT. In the meantime, it has been decided to incorporate the GDPR readiness planning into this project. So, while the original deliverables while soon be signed off, the closure will be extended as the project scope is changed. The steps to report this are under way and will be submitted to WIS shortly.

 

Report by David Watters for January 2018

Achievements

  • Further revisions made on Sharepoint site
  • GDPR mailing list established
  • Initial discussions on extending scope of project to include 'Readiness' work

Issues

  • Delivery of Sharepoint & sign-off delayed further
  • Closure delayed
  • Project scope, effort and milestones to be revised

Next steps

  • Finalise content of Sharepoint site and share with wider group
  • Sign off deliverables
  • Start work on 'Readiness' aspect of project

 

 

 

 

 

ISG008

Projects Website Enhancements

Milestones

30-Mar-2018 Closure

RAG Status

AMBER

Report for January 2018

Achievements

  •  

Issues

  •  

Next Steps

  •  

ISG009

Alma Library Management Platform 2-Way Feed with E-Financials

Milestones

02-Feb-2018

Planning

11-May-2018

Business Analysis

25-May-2018

Delivery

08-Jun-2018

Closure

 

RAG Status

AMBER

Report by Emma McNab for January2018

Achievements in Last Period

  • Brief updated
  • On-going discussions with key stakeholders

Issues

Issue 2: There has been a delay in development of the brief due to withdrawal of Finance Lead and delay in identifying replacement Lead. 

Next Steps

  • Brief signed off
  • Planning completed

ISG010

MyEd Database Migration to Oracle 12

Milestones

15/12/2017 - Planning

30/03/2017 - Delivery

27/04/2017 - Closure

RAG Status

GREEN

Report by Richard Bailey for January 2018

Achievements in last period

  • Lisa Dawson confirmed as the Project Stakeholder
  • Stakeholders and Project Team agreed
  • Resource secured
  • Planning completed
  • Project Manager has completed a Brief and it is to be submitted to WIS for approval 02/02/2018

Issues / Risks

Next Steps

  • Seek approval for Brief at WIS (02/02/2018)
  • Begin work packages

 

ISG011

IS Apps Procurement Question Set

Milestones

Target Datesort descending Title
16-Feb-2018 Planning
20-Apr-2018 Question Set Checkpoint 1 (after 4th question set review)
18-May-2018 Question Set Governance
15-Jun-2018 Question Set Checkpoint 2 (after 8th question set review)
20-Jul-2018 Completion of the Procurement Question Set Review
27-Jul-2018 Closure

RAG Status

RED

Report by Andy Stewart for January 2018

Achievements

  • Question Sets
    • Initial meetings held with Procurement, Information Security and Accessibility, who have agreed to participate in the review of the question sets 
    • Clarification regarding ownership of the question sets regarding Technical and Usability 
    • Latest copies or the question sets received with regards to Information Security and Accessibility
  • Project brief updated and circulated to the project team for approval 
  • Project re-planned to accommodate delay in commencing Question Set review 

Issues

  • Completion of planning phase delayed to clarify aspects of the project brief regarding project team members, project milestones and Question Set owners.  This then subsequently impacted on the commencement of the Question set 

Next Steps

  • Complete project planning phase
  • Confirm scheduling of Question set review
  • Commence review of question sets

RAG Status

Red  - Project delivery extended from early June to late July resulting from delay in the progressing concerns regarding original project brief

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary

ISG003

Projects Website Migration

Category: Compliance

Project Closed on 12 May 2017.

ISG005

Monitoring IT and Library Business Service Readiness For Start of Term 2017/18

Project Closed on 3 November 2017

ISG007

Architecture Repository Implementation

Project Closed on 3 November 2017

 