Report for October 2017

Report Date
October 2017

Report compiled by Adam Wadee

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

 

 

 

 

Section Two: Projects Not Started

 

Project Info Programme Manager's Commentary

ISG010

MyEd Database Migration to Oracle 12

Project to start in November

 

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

ISG006

Establish GDPR Support Resources

 

Milestones

24-Nov-2017                                       Final delivery of online resources Deliver                         
24-Nov-2017 Delivery of advice and support documentation                                                      Deliver
01-Dec-2017 Delivery sign-off Deliver
15-Dec-2017 Project closure Close

RAG Status

RAG status is AMBER because of delays in delivering website and SharePoint site

Report by David Watters for October 2017

Achievements

  • ISG Working Group: Group members continuing to work on data registers; follow-on workshop arranged for December.
  • Ongoing consultations with project team & senior supplier, and PMs on other GDPR projects.

Issues

  • Remaining milestones extended
  • Project health check requested by Project Services head (actions to follow)
  • Web pages to be reviewed and signed off by Records Management
  • Sharepoint site still to be made available.

Next steps

  • Public version of web pages to be reviewed and published.
  • ISG 'GDPR Group' to have workshop and next steps to be determined.
  • Sharepoint site to be prepared for use by all.

 

 

 

ISG008

Projects Website Enhancements

Milestones

23-Nov-2017 Final Deployment
30-Nov-2017 Closure

RAG Status

AMBER

Report by Steph Ruthven for October 2017

Achievements

  • Ed Web distribution update applied successfully to LIVE after UAT and Regression testing
  • Lessons Learned log signed off in TEST
  • Some bug fixes addressed
  • Changes to Risk log received from Sponsor

Issues

  • More time spent on the distribution update than planned in order to make sure the custom modules for the Projects Website were properly integrated
  • Limited time with Developer, who will not be available after 11 November

Next Steps

  • Deploy final release to LIVE containing benefits log and Change dashboard
  • Plan for further work required on permissions changes

ISG009

Alma Library Management Platform 2-Way Feed with E-Financials

Milestones

30/11/2017 - Planning

30/03/2017 - Delivery

15/04/2017 - Closure

RAG Status

GREEN

Report by Emma McNab for October 2017

Achievements

  • Project started on 3rd November.
  • Kick-off meetings held with business partners.

Issues

  • None

Next Steps

  • Complete project brief.

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary

ISG003

Projects Website Migration

Category: Compliance

Project Closed on 12 May 2017.

ISG005

Monitoring IT and Library Business Service Readiness For Start of Term 2017/18

Project Closed on 3 November 2017

ISG007

Architecture Repository Implementation

Project Closed on 3 November 2017

 