Report for July 2017

Report Date
July 2017

Report compiled by Adam Wadee

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

 

Section Two: Projects Not Started

 

Project Info Programme Manager's Commentary
None  

 

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

ISG005

Monitoring IT and Library Business Service Readiness For Start of Term 2017/18

 

Milestones

25-Aug-2017 Agreed Staff Contact Lists
11-Sep-2017 Start of Welcome Week (External Milestone)
18-Sep-2017 Start of Teaching Week 1 (External Milestone)
25-Sep-2017 Start of Teaching Week 2 (External Milestone)
13-Oct-2017 Delivery Sign Off Following Start of Term
27-Oct-2017 Closure

RAG Status

GREEN

 

Report by Colin Watt for July 2017

Achievements in Last Period

Issues

  • No major issues at present.

Next Steps

  • Complete  Agreed Staff Contact Lists milestone.
  • Ensure ongoing dialogue with the various groups involved in start of term activities so that information is reviewed and updated at least weekly.
  • Review risks with Project Team.

ISG006

Establish GDPR Support Resources

 

Milestones

11-Aug-2017 Analysis & Design sign-off Analyse
14-Sep-2017 Build sign-off Build
24-Oct-2017 Acceptance sign-off Accept
27-Oct-2017 Final delivery of online resources Deliver
27-Oct-2017 Delivery of advice and support documentation Deliver
03-Nov-2017 Delivery sign-off Deliver
17-Nov-2017 Project closure Close

RAG Status

GREEN

Report by David Watters for July 2017

Achievements

  • Design stage of website in draft
  • Requirements for Sharepoint site being drafted
  • Further consultations with project team

Issues

  • None

Next steps

  • Sharepoint site to be requested
  • ISG 'GDPR Group' to have first meetings
  • Initial advice to be prepared for University staff and made available.

 

 

ISG007

Architecture Repository Implementation

Milestones

28-Jul-2017 Phase 1 delivery
28-Aug-2017 Phase 2 delivery
29-Aug-2017 Project closure

RAG Status

GREEN

Report by Wilbert Kraan for July 2017

Achievements

  • The vendor has been paid, in time for the previous financial year.
  • Dev tech resource has been secured for installation.
  • Software components and keys have been received, and installed were relevant.

Issues

  • On closer examination of the software components, we concluded that no new server needed to be installed; the 'enterprise server' component is an SVN server, and the 'publisher' component is a static set of HTML, PNG and JavaScript. We're planning to use the University's existing SVN and web co-hosting services to support these components.
  • If the university services integration works, a second phase won't be necessary.

Next steps

  • Complete a TAD.
  • Test the integration of ABACUS with the university SVN and web hosting services.
  • Receive administration training from the vendor.
  • Provide a news item and service description.

ISG008

Projects Website Enhancements

Milestones

11-Aug-2017 End of Planning
24-Aug-2017 Release 3 Deployment
31-Aug-2017 Release 4 Deployment
08-Sep-2017 Closure

RAG Status

GREEN

Report by Steph Ruthven for July 2017

Achievements

  • Contract Drupal Developer recruited and started
  • First release deployed to LIVE of bug fixes
  • Project initiated

Issues

  • Project work started before initiation

Next Steps

  • Complete planning
  • Deploy release 2 to LIVE
  • Prioritise remaining user stories

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary

ISG003

Projects Website Migration

Category: Compliance

Project Closed on 12 May 2017.

 

AttachmentSize
Image icon isg-rag-jul-17v2.jpg64.58 KB
Image icon isg-resources-jul-17.jpg139.9 KB

Documentation

Not available.