Report for March 2016

Report Date
March 2016

Report compiled by Adam Wadee

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

 

Section Two: Projects Not Started

 

Project InfoProgramme Manager's Commentary
None 

 

 Section Three: Projects in Progress

 

Project InfoProject Managers Commentary

ISG003 (In-year)

Projects Website Migration

Category: Compliance

Milestones

Target dateTitle
13-May-2016End of development phase
16-May-2016Go-live
27-May-2016End of maintenance phase
10-Jun-2016Project closure

RAG Status: GREEN

Report by Dawn Holmes for March 2016

Achievements this period

  • Basic website has been developed.  New projects can be added, templates and blank pagescan be added to it, and the first of the logs (risk log) is in place.

Issues

  • Resource conflicts for the Project Sponsor's time has resulted in the project progressing without clear guidance on the prioritiesfor the new website.

Next steps

  • Development of project templates (e.g. simple, software, agile)
  • Development of other project logs
  • Deployment of application to Test environment
  • Production of draft technical documentation (TAD)

Section Four: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary
 

 

 

 

 

 

 

 

 

 

Documentation

Not available.