Report for May 2018
- Report Date
- May 2018
Report compiled by Andrew Stewart (IS Apps Programme Manager) for David Montgomery(Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Forward Look

Resources Position

Section Two: Projects Not Started
There are no not started projects currently planned for 17/18.
| Project Info | Programme Manager's Commentary |
|
|
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||||
|
Category: Discretionary (Sponsor funded) Remaining Milestones
RAG Status : AMBER
|
Report by Nikki Stuart for May 2018 Achievements in the last period
Issues
Next steps
RAG - AMBER - CHANGE: Additional Phase 3 requirements agreed extended the milestones and budget.
|
||||||||||
|
Fire Safety Analysis Category: Discretionary (Sponsor funded) Milestones
RAG Status : AMBER |
Report by Lee-Ann Simpson for May 2018
Achievements in the last period
Issues
Next Steps
Rag Status: Change: Delivery milestone extended by weeks to enable a further solution to be reviewed
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
|
CSG011 Totara Pilot Category: Discretionary (Sponsor funded) |
Project closed Jan 18. Closure Report can be found at https://www.projects.ed.ac.uk/project/csg011/closure-report |
|
CSG Learning & Development - Rollout and Further Integration; Category: Discretionary (Sponsor funded) |
Withdrawn following decision not to roll out the L&D system. See closure report for CSG011 above for information. |
| Attachment | Size |
|---|---|
| 31.46 KB | |
| 25 KB |
