Report for April 2018

Report Date
April 2018

 

Report compiled by Andrew Stewart (IS Apps Programme Manager) for David Montgomery(Programme Owner)

 

Section One: Programme Commentary, RAG and Resources Update

Progress continues to made with the current active projects and no matters of concern reported.

 

Forward Look

 

Resources Position

 

 

 

Section Two: Projects Not Started

There are no not started projects currently planned for 17/18. 

Project Info Programme Manager's Commentary

 

 

 

 

Section Three: Projects in Progress

Project Info Project Managers Commentary

CSG012

ESPA

Category: Discretionary (Sponsor funded)

 Milestones

25-Apr-2018 Phase 2 - Deployment Sign Off
04-May-2018 Phase 3 - Design Sign Off
11-May-2018 Phase 3 - Build Sign Off
25-May-2018 Phase 3 - UAT Sign off
01-Jun-2018 Phase 3 - Deployment to LIVE
15-Jun-2018 Phase 3 - Deployment Sign Off
15-Jun-2018 Project Closure

 

RAG Status : AMBER

 

Report by Nikki Stuart for April 2018      

Achievements in the last period

  • Completion of build and pre-deployment checks
  • UAT sign off 
  • Deployment to LIVE for Phase 2 JIRAs
  • Phase 2 deployment sign off
  • Complete SLA
  • Phase 3 requirements, budget and timeline agreed

Issues

  • none

Next steps

  • Complete graphic design  for Phase 3
  • Refresh TEST ahead of data upload of Sql data
  • test upload to TEST of data upload process
  • Build Phase 3 enhancements
  • start UAT for Phase 3 enhancements

RAG - AMBER - CHANGE: Additional Phase 3 requirements requested by Sponsor to complete project. 

 

 

CSG013

Fire Safety Analysis

Category: Discretionary (Sponsor funded)

 Milestones

  Title
06-Apr-2018 Analysis
04-May-2018 Delivery
18-May-2018 Closure

RAG Status : AMBER

Report by Lee-Ann Simpson for April 2018

 

Achievements in the last period

  • Project plan revised to include delay due to Archibus demo which took place on the 24th April.

  • Requirements gathering workshop undertaken with Estates to determine joint requirements for the Archibus demo.
  • Additional market supplied solutions identified and reviewed as part of the Early Market engagement.
  • Issues 

  • In March, the business lead has expressed concerns regarding a potential delay to reviewing the Archibus WebCentral modules and the impact of the project being extended by four week.  This was reviewed by the project team and the project plan was updated to reflect the delay.
  • Due to A/L commitments of the Fire Safety Team during April, a subsequent Webinar has been requested by Archibus to allow a bespoke demonstration to be conducted.
  • Next Steps 

  • Webinar dates to be confirmed for the Fire Safety demonstration.
  • Complete gap analysis review once Fire Safety demo has been undertaken with regards to: 
    • Existing Archibus modules
    • Potential market supplied solutions  
  • Continue business report.
  • ARUP supplier demonstration to be conducted by Fire Safety Team.
  • Review requirements with Fire Safety team and project sponsor to understand if they are all still in scope for this project or not.

Rag Status: AMBER

Change: Project delivery has been delayed by 4 weeks due to the scheduling of selected Archibus WebCentral modules demonstration by the supplier and subsequent Webinar for the Fire Safety Team to account for A/L during the initial demonstration. This has been approved by the project team and sponsor

 Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary

CSG011

Totara Pilot

Category: Discretionary (Sponsor funded)

Project closed Jan 18. Closure Report can be found at https://www.projects.ed.ac.uk/project/csg011/closure-report 

CSG Learning & Development - Rollout and Further Integration;

Category: Discretionary (Sponsor funded)

Withdrawn following decision not to roll out the L&D system. See closure report for CSG011 above for information. 
AttachmentSize
Image icon 201804-rag.png25.67 KB
Image icon 201804-resources.png29.31 KB

Documentation

Not available.