Report for October 2017

Report Date
October 2017

 

Report compiled by Nikki Stuart (IS Apps Programme Manager) for Charles Hill (Programme Owner)

 

Section One: Programme Commentary, RAG and Resources Update

 

 

Forward Look

 

 

 

Resources Position

 

 

 

Section Two: Projects Not Started

 

Project Info Programme Manager's Commentary

CSG Learning & Development - Rollout and Further Integration;

Category: Discretionary (Sponsor funded)

to be withdrawn following decision to not rollout the L&D system to CSG

 

 

Section Three: Projects in Progress

Project Info Project Managers Commentary

CSG011

Totara Pilot

Category: Discretionary (Sponsor funded)

 Milestones

To be reset following no go decision

RAG Status : AMBER

Report by Ben Armstrong for October 2017

Achievements this period

  • User Group met on 24th October to review success of pilot, incorporating feedback from user survey and whether scenarios have been met

Issues

  • The user group decided that the pilot had not sufficiently met their success criteria and a decision was taken not to proceed past the pilot.  Further detail will be summarised in the project closure report.  For this reason, the project is marked as RED this month due to the change in scope not to roll out the product more widely.  However, this issue has been resolved through the 'no go' decision and agreement to close the project following the review of the pilot.

Next Steps

  • Dev Tech to decommission Totara build
  • Project closure report incorporating lessons learnt

CSG012

ESPA

Category: Discretionary (Sponsor funded)

 Milestones

10-Nov-2017  24-Jul-2017 Development Build Sign-off
13-Nov-2017  25-Jul-2017 Install in Test
14-Nov-2017  27-Jul-2017 Integration / system test sign-off
22-Nov-2017  04-Aug-2017 User Acceptance sign-off
22-Nov-2017       07-Aug-2017 Deploy to live
22-Nov-2017 08-Aug-2017 Deployment / handover to support sign-off
22-Nov-2017  22-Aug-2017 Post-implementation support sign-off
30-Mar-2018  29-Aug-207 Project Closure

 

RAG Status : GREEN

 

Report by Nicholas Graham for October 2017      

 Achievements in the last period

  • Rohallion engagement confirmed.  Development begun. 
  • QA by IS Development Services begun.
  • Demonstration of desktop re-theming delivered to schedule 30/10/17. 
  • Customer proposed re-focusing UAT activities on content and editorial work by ESPA team. 
  • Preparation for cutover to live service on 22/11/17 remains on schedule. 
  • Drupal support responsibilities agreed.  

Issues

  • None.      

Next steps

  • Completion of increment 1 development work. 
  • Sign-off by customer stakeholder. 
  • Completion of live environment preparation. 
  • Cutover of delivered website to schedule on 22/11/17.

                                                                                                                                                 

CSG013

Fire Safety Analysis

Category: Discretionary (Sponsor funded)

 Milestones

TBA

RAG Status : GREEN

Report by Andy Stewart for October 2017    

 

Achievements

  • Project initiated and project code (CSG013) assigned
  • Initial project briefing with business analyst

Issues 

  • None

Next Steps 

  • Complete project planning phase 
  • Commence business analysis 

 Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary

 

 

 

 
AttachmentSize
Image icon csg_ragoct17.jpg88.37 KB
Image icon csg_resourcingoct17.jpg91.04 KB

Documentation

Not available.