Report for September 2017

Report Date
September 2017

 

Report compiled by Nikki Stuart (IS Apps Programme Manager) for Charles Hill (Programme Owner)

 

Section One: Programme Commentary, RAG and Resources Update

 

 

Forward Look

 

 

 

Resources Position

 

 

 

Section Two: Projects Not Started

 

Project Info Programme Manager's Commentary

CSG Learning & Development - Rollout and Further Integration;

Category: Discretionary (Sponsor funded)

This is a funded project that was included as a place holder should CSG decide to deliver further integration for the L&D (Totara) system. A decision on this should be made October 2017. 

 

 

Section Three: Projects in Progress

Project Info Project Managers Commentary

CSG011

Totara Pilot

Category: Discretionary (Sponsor funded)

 Milestones

Target date

Title

Complete

28/02/17

Planning 

YES

29/09/17

Phase 1 Delivery

NO

31/10/17 Phase 2 Delivery NO

30/11/17

Closure

NO

 

RAG Status : AMBER

Report by Ben Armstrong for Sep 2017

Achievements this period

  • Pilot completed on 30th September
  • Support arrangements agreed in principle, with planned transfer of ownership to HR Systems expected from 1st December
  • User survey issued to staff and line managers in pilot
  • System Administrator Guide refined and circulated
  • Mandatory training requirement is capable of being accommodated within standard Totara offering and has been tried by Estates
  • Equality and Impact Assessment has been published

Issues

  • The transfer to HR Systems support of 1st December is about a month behind the original schedule for transfer to support - this is likely to impact budget as well as time so both indicators are showing as AMBER this month

  • Development Technology raised requirement for Information Security team to review the proposed security and encryption proposal for the automated staff feed

Next Steps

  • Meeting with Information Security team to review the proposed security and encryption proposal for the automated staff feed
  • Test the automated staff and organisations feed
  • User Group 24th October to review success of pilot, incorporating feedback from user survey and whether scenarios have been met
  • Meetings to be planned with HR Systems to take place early November including training (potentially from supplier)
  • Final recommendation following Event Booking integration feasibility

CSG012

ESPA

Category: Discretionary (Sponsor funded)

 Milestones

Target date

Title

Complete

21/04/17

Brief sign-off 

YES

09/06/17

Planning sign-off

YES

18/08/17 Discovery end YES

18/08/17

Back-end design sign-off

YES

22/11/17     

Deploy   to live (1)                

 

NO             

30/03/18     

Project closure                    

NO             

 

RAG Status : GREEN

Report by Nicholas Graham for September 2017        

                             

Achievements in the last period

  • Design products delivered and reviewed. 
  • Rohallion Ltd engagement agreed in principle and resource availability confirmed. 
  • ResearchFish and Thompson/Reuters feeds confirmed as out of scope of development.  
  • Faceted search confirmed as out of scope for Increment 1.
  • Technical preparation for development completed.
  • Customer confirmed IS should support delivered website.
  • Customer confirmed that ERI will take on support of SQL Server & Access components, not IS. 
  • Delivery timescales of 15/11/17 (Increment 1) agreed with stakeholders and authorised by WIS. 
  • Second delivery increment Jan 2018 - March 2018 agreed with stakeholders and authorised by WIS.   

Issues

  • None.     

Next steps

  • Finalise Rohallion contractual engagement.
  • Begin development. 
  • First-cut review of pages  of website w/c 30/10/17. 
  • Agree Drupal application support responsibilities. 

                                                                                                                                                 

 Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary

 

 

 

 
AttachmentSize
Image icon csg_ragsept17.jpg74.73 KB
Image icon csg_resourcingsept17.jpg82.4 KB

Documentation

Not available.