CSG011
Totara Pilot
Category: Discretionary (Sponsor funded)
Milestones
|
Target date
|
Title
|
Complete
|
|
28/02/17
|
Planning
|
YES
|
|
29/09/17
|
Phase 1 Delivery
|
NO
|
| 31/10/17 |
Phase 2 Delivery |
NO |
|
30/11/17
|
Closure
|
NO
|
RAG Status : AMBER
|
Report by Ben Armstrong for Sep 2017
Achievements this period
- Pilot completed on 30th September
- Support arrangements agreed in principle, with planned transfer of ownership to HR Systems expected from 1st December
- User survey issued to staff and line managers in pilot
- System Administrator Guide refined and circulated
- Mandatory training requirement is capable of being accommodated within standard Totara offering and has been tried by Estates
- Equality and Impact Assessment has been published
Issues
-
The transfer to HR Systems support of 1st December is about a month behind the original schedule for transfer to support - this is likely to impact budget as well as time so both indicators are showing as AMBER this month
-
Development Technology raised requirement for Information Security team to review the proposed security and encryption proposal for the automated staff feed
Next Steps
- Meeting with Information Security team to review the proposed security and encryption proposal for the automated staff feed
- Test the automated staff and organisations feed
- User Group 24th October to review success of pilot, incorporating feedback from user survey and whether scenarios have been met
- Meetings to be planned with HR Systems to take place early November including training (potentially from supplier)
- Final recommendation following Event Booking integration feasibility
|
|
CSG012
ESPA
Category: Discretionary (Sponsor funded)
Milestones
|
Target date
|
Title
|
Complete
|
|
21/04/17
|
Brief sign-off
|
YES
|
|
09/06/17
|
Planning sign-off
|
YES
|
| 18/08/17 |
Discovery end |
YES |
|
18/08/17
|
Back-end design sign-off
|
YES
|
|
22/11/17
|
Deploy to live (1)
|
NO
|
|
30/03/18
|
Project closure
|
NO
|
RAG Status : GREEN
|
Report by Nicholas Graham for September 2017
Achievements in the last period
- Design products delivered and reviewed.
- Rohallion Ltd engagement agreed in principle and resource availability confirmed.
- ResearchFish and Thompson/Reuters feeds confirmed as out of scope of development.
- Faceted search confirmed as out of scope for Increment 1.
- Technical preparation for development completed.
- Customer confirmed IS should support delivered website.
- Customer confirmed that ERI will take on support of SQL Server & Access components, not IS.
- Delivery timescales of 15/11/17 (Increment 1) agreed with stakeholders and authorised by WIS.
- Second delivery increment Jan 2018 - March 2018 agreed with stakeholders and authorised by WIS.
Issues
Next steps
- Finalise Rohallion contractual engagement.
- Begin development.
- First-cut review of pages of website w/c 30/10/17.
- Agree Drupal application support responsibilities.
|