Report for December 2019

Report Date
December 2019
 

 

Report by Susan Ridder-Patrick (MVMLAT Programme Manager) for Philippa Burrell (MVMLAT Programme Owner) and Catherine Elliot (MVM Portfolio Owner)

Distribution:

  • Vet and Medical School sub-group IT meeting
  • College Administration Team (CAT) meeting
  • College Undergraduate Learning and Teaching (CULT) committee
  • Post Graduate Learning and Teaching (PGLTC) committee
  • Excerpts taken into CSG report

Section One: Programme Commentary, RAG and Resources Update

Commentary

Programme status: The overall status of the MVMLAT programme is AMBER due to continuing impact from three top risks and two continuing issues.

Risks raised in November

  • Departure of Head of Digital Learning Applications and Media team: New appointment has taken place but this does not reduce the risk to the programme from loss of historical knowledge and experience.
  • Industrial action: This programme's work has been impacted by colleagues participating in industrial action which is expected to continue in 2020.
  • Insufficient resources: The programme has completed estimations for the first projects in the plan and this has resulted in the need to hold a prioritisation meeting to assess what is realistically possible to deliver in 19/20. Prioritisation needs to be confirmed at the start of 2020 to ensure the right work is completed.

Issues

The programme is still being impacted by the issues raised in October:

Project highlights

  • MVM132: Project milestones were revised as MVM lead had to prioritise supporting exams
  • MVM134: Project was impacted by industrial action but is due to conclude development Mid-Jan 2020
  • MVM136: Successful first Admissions Assessment days - outcome achieved
  • MVM135: Project initiation
  • MVM137: Project initiation

Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.

Forward Look - December 2019  

 

Section Two: Projects Not Started 

The Not Started projects in the MVMLAT programme were discussed at the 22 October 2019 programme meeting and the table below reflects the programme's current position. Due to competing priorities and lack of capacity in MVM, there are a number of projects noted as not currently planned for inclusion in 19/20.

Project Programme Manager's Commentary
MVM516 BMS Honours Portal Project Start date TBC, currently provisionally Jan 2020 with delivery in May 2020 but scope discussions to be concluded first
Curriculum Map Start date TBC , currently provisionally May 2020 with delivery in October 2020
Student EMS Placement Management Starting Jan 2020 with delivery in June 2020 
House Hub Start date TBC 
Labyrinth Start date TBC
PathCAL Start date TBC
Shiny Server Start date TBC
MVM102 Innovative Technology review TBC - not currently planned in 19/20
MVM106: Student Print Strategy TBC if still required - not currently planned in 19/20
MVM109 Technology to support communications with potential students. TBC if covered by SEP SRA Enquiry Management - not currently planned in 19/20
MVM110 Technology to support Open Educational Resources (OER) TBC - not currently planned in 19/20
MVM113 Technology to support student portfolios TBC if still required - not currently planned in 19/20

 

Section Three: Projects in Progress

MVM Learning and Teaching Projects Update

MVM112: Technology to support simulation teaching - RAG Status: 

Report by Alan Gilchrist  ***Commentary from November 2019***

Achievements this period

  • Limited progress due to project manager's annual leave.  Simulated Patient Co-Ordinator has viewed another organisation's database used for a similar purpose and is going to pass on details of the database to the project manager to see if it could fulfil our needs and be used within the University.

Issues

  • None

Next Steps

  • Receive details of other organisation's database and evaluate the possibility of its use within our context.
  • Continue development of Simulated Patient database.
  • Create an initial draft report outlining the University’s simulation equipment currently available within the Chancellor’s Building Clinical Skills Centre and WGH MEC.  Include proposed maintenance costs, annual recurring costs and replacement cycles.

MVM125: Connectivity - Off-campus 2018/19 - RAG Status: 

Report by Alan Gilchrist  ***Commentary from November 2019***

Achievements this period

  • Limited progress due to project manager's annual leave.
  • Have received response from clinical contact in Forth Valley that eduroam is indeed now installed in the hospital and that students are using it.

Issues

  • None

Next Steps

  • Create a suitable PC build configuration for the PAEP library and install on the computers on site.
  • Receive suggested options for restoring eduroam connectivity in NHS Lanarkshire.
MVM132 MBChB ranking reports in BI Suite  - RAG Status: GREEN
Report by Susan Ridder-Patrick

Achievements this period

  • Delivery and Closure milestones revised as Business Lead was unable to complete review of reports in LIVE due to unexpected leave and the need to priories Exams.

Issues

  • None

Next Steps

  • Completion of user checks on LIVE report
  • Closure

MVM134 MBChB Evaluation System - RAG Status: AMBER

Report by Andrew Millington 

Achievements this period

  • Added in the ability to share reports. A key feature of the system used to distribute evaluation results
  • Complete report filters
  • Give administrators the ability to redact free text responses that contain inappropriate material
  • Provide ability to download the raw data from reports in CSV format

Issues

  • None

Next Steps

  • Implement PDF downloads of reports
  • Implement automatic generation of shares for years, blocks, and NHS boards

 

MVM135 Upgrading of Teaching Spaces 2019/20 - RAG Status: 

Report by Alan Gilchrist  ***No Commentary from November 2019 as project initiated***

Achievements this period

  •  

Issues

  •  

Next Steps

  •  

MVM136 Practique Roll-out - RAG Status: GREEN

Report by Susan Ridder-Patrick

Achievements this period

  • Successful Admissions Assessment days took place for the first time with no issues during the days and with great feedback from the assessors on how straightforward the process and software was. 
  • Admissions lead has begun to use the data and is delighted with the information - the desired outcome has been achieved.
  • Lessons learned completed for Admissions - key success factor was how thoroughly prepared the Admissions team were for the Exam Fit days in September, which meant their requirements were very clearly understood.

Issues

  • College is working with supplier on option to have a separate TEST instance for the Vets/BMTO.

Next Steps

  • Business completing agreed steps to ensure the MBChB HCP Admission Assessment days take place smoothly
  • Detailed planning for the Vets and BMTO work

MVM137 Upgrading of Student Computer Labs , Teaching and Meeting Room PC 19/20 - RAG Status: 

Report by Alan Gilchrist  ***No Commentary from November 2019 as project initiated***

Achievements this period

  •  

Issues

  •  

Next Steps

  •  

MVM516 BMS - Honours Project Portal Future Support - RAG Status: AMBER

Report by Susan Ridder-Patrick

Achievements this period

  • None in this period

Issues

  • This project was planned to start mid-January in December's programme priority discussion but discussions on scope are continuing which may delay the start of the project

Next Steps

  • Agree scope of the project and confirm start date

Projects outwith the MVM Portfolio Update

Report by Alan Gilchrist and Anne-Marie Scott (LTW):

EEMeC and EEVeC

The programme has been and continues to complete projects to close down functionality on both EEMeC and EEVeC with a view to eventually decommissioning.  There is a requirement to maintain (read only) access for a period and the programme is in the process of determining those dates for its 3 year plan.

 

TEL056: Edinburgh Surgery Online Learn go-live - RAG Status: BLUE - Closed

DTP001: Apps to User Devices - RAG Status: AMBER

Summary of Achievements in last period:

  • Progress on actions 
    • Training videos - reviewed and updated with subtitle to comply with Accessibility Legislation
    • Access on EUCLID - solution implemented
    • OneDrive visibility- Work around implemented and available via Apps Ed FAQ web page
  • CAHSS - testing plan restarted and ongoing
  • MVM - await sign-off for remaining applications
  • Performance/ Load testing unable to be completed prior to soft launch
  • Note: Soft Launch date  and Communication Plan with Project Board for approval

 

Risks and Issues

  • No new issues raised

Next Steps 

  • 'delta' document outlining the infrastructure testing to be completed with signed off testing
  • Communications Plan approval
  • Approval of go live date
  • schedule project board meeting for post-go live 

 

HSS022: CAHSS WAM Deployment  - RAG Status: 

Achievements this period

  • Closure report drafted and circulated

Issues

  • Delay due to lack of availability from programme manager to complete closure

Next Steps

  • Finalise Closure

TEL057: Learn Foundations - RAG Status: 

Achievements this period

  • Phase One School reports completed and sent to key contacts;
  • Continued on the Phase Two work streams;
  • Created the Evaluation baseline;
  • Completed Lessons Learned report for Phase One with the project team;
  • Began to schedule the 2nd round of engagement sessions with the non-phase one Schools.
  • UX recruitment and activity continued.

Issues

  • As with November, industrial action has impacted the progress of the project with various stakeholders being away from the office before moving into the Christmas and New Year period where no UX activity could be scheduled.  No impact to the overall timeline of the project.

Next Steps

  • Continue on the Phase Two work streams.
  • Undertake the 2nd round of engagement sessions with the non-phase one Schools.
  • Gain commitment from the non-phase one Schools to join the Learn Foundations project within Phase Two.
  • UX recruitment and activity to be continued.
  • User Groups to be undertaken for both Staff and Students within January.
  • Phase Two review of the programme of training to be undertaken.

Section Four: Closed or Withdrawn Projects

Only those projects closed from 28th June 2019 onwards are included in this table. A full history of completed projects is available on the programme's website.

Project Info Project Manager's Commentary
MVM126 Upgrading of student computer labs, teaching and meeting room PCs 2018/19 This project started in October 2018 and closed on 28 June 2019. The Closure report is now available.
MVM129 Support for OSCEs in Practique for MBChB This project started in June 2018 and closed on 28 June 2019. The Closure Report is now available.
MVM131: Migration of 12 applications developed in Biomedical Sciences to central support - Analysis & Strategy This project started in December 2018 and closed on 28 June 2019. The Closure Report is available to view.
MVM133: CMVM Curriculum Mapping Tool - Requirements This project started in April 2019 and closed on 9th August 2019.  The Closure Report is available to view. 
MVM130: Upgrading of teaching spaces 2018/19 This project started in October 2018 and closed on 1st November 2019. The Closure Report is available to view.

Section Five: Programme Meeting Minutes

Minutes for all programme meetings are available on the MVMLAT website. Only the most recent five meetings direct links are included in this table:

Date

Comments

10 December 2019 Programme Review Monthly Meeting - November 2019
12 November 2019 Programme Review Monthly Meeting - October 2019
22 October 2019 Programme Review Monthly Meeting - September 2019
9 September 2019 Programme Review Monthly Meeting - August 2019
19 August 2019 Programme Review Monthly Meeting - July 2019

Section Six: MVM Portfolio Projects Update 

The MVM Portfolio contains three programmes: CMVM Learning and Teaching - MVMLAT (this programme); CMVM Business Administration - MVMBUS and CMVM Research - MVMRES. Information on current work in MVMBUS and MVMRES are available on the following websites:

AttachmentSize
Image icon forward_look.png62.16 KB
Programme Status
RAG Status
Overall
AMBER
Has formal escalation taken place?
No

Programme Info