Report for August 2019
- Report Date
- August 2019
![]()
Report by Susan Ridder-Patrick on behalf of Alan Gilchrist (MVMLAT Programme Managers) for Philippa Burrell (MVMLAT Programme Owner) and Catherine Elliot (MVM Portfolio Owner)
Distribution:
-
Vet and Medical School sub-group IT meeting
-
College Administration Team (CAT) meeting
-
College Undergraduate Learning and Teaching (CULT) committee
-
Post Graduate Learning and Teaching (PGLTC) committee
-
Excerpts taken into CSG report
Section One: Programme Commentary, RAG and Resources Update
Commentary
The new 2019/20 session starts with 5 ongoing projects:
- MVM132 MBChB ranking reports in BI Suite
- MVM112: Technology to support simulation teaching
- MVM125: Connectivity - Off-campus 2018/19
- MVM130: Upgrading of teaching spaces 2018/19
- MVM133: Curriculum Mapping Tool - Requirements
The overall status of the MVMLAT programme is GREEN given the significant effort achieved in the MVM130 Upgrading of Teaching Spaces project.
Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.
Forward Look - August 2019

Section Two: Projects Not Started
The un-prioritised projects from last session were reviewed at Programme Review Monthly Meeting - August & September 2018. Two projects were no longer relevant and have been withdrawn.
The remaining projects below were expected to start in 2018/19. However, due to competing priorities and lack of capacity in MVM, these were not started in 2018/19 and will be considered for next session (2019/20).
| Project | Programme Manager's Commentary |
|---|---|
| MVM102 Innovative Technology review | TBC |
| MVM106: Student Print Strategy | TBC |
| MVM109 Technology to support communications with potential students. | TBC |
| MVM110 Technology to support Open Educational Resources (OER) | TBC |
| MVM113 Technology to support student portfolios | TBC |
Section Three: Projects in Progress
MVM Learning and Teaching Projects Update
|
MVM112: Technology to support simulation teaching - RAG Status: GREEN Report by Alan GilchristAchievements this period
Next Steps
|
|
|
MVM125: Connectivity - Off-campus 2018/19 - RAG Status: GREEN Report by Alan GilchristAchievements this period
Issues
Next Steps
|
|
|
MVM130 Upgrading of teaching spaces 2018/19 - RAG Status: GREEN Report by Alan GilchristAchievements this period
Issues
Next Steps
|
|
MVM132 MBChB ranking reports in BI Suite - RAG Status: AMBER
Report by Susan Ridder-PatrickAchievements this period
Issues
Next Steps
|
MVM Portfolio Projects Update
| MVM522 project is now closed |
Projects outwith the MVM Portfolio Update
Report by Alan Gilchrist and Anne-Marie Scott (LTW):
|
TEL056: Edinburgh Surgery Online Learn go-live - RAG Status: AMBER Time continues to be Red as Ophthalmology work continues to be significantly behind schedule. Scope changed to amber as most programmes will not begin Semester 2 content updates until closer to Semester 2. TCHM/GCHM Semester 2 updates have been completed. A number of milestones due at the end of March have not been achieved, and the backup plan to achieve these by the end of May has also not been achieved. The Academic eFacilitators are aware of the deadlines and also of the Learn to the Cloud down-time in July. |
|
|
DTP001: Apps to User Devices - RAG Status: GREEN Project Board Meeting held for go live approval
|
|
|
HSS022: CAHSS WAM Deployment - RAG Status: GREEN Achievements this period
Next Steps
|
Other Updates
|
No additional updates in this period |
Section Four: Closed or Withdrawn Projects
| Project Info | Project Manager's Commentary |
|---|---|
| MVM126 Upgrading of student computer labs, teaching and meeting room PCs 2018/19 | This project started in October 2018 and closed on 28 June 2019. The Closure report is now available. |
| MVM129 Support for OSCEs in Practique for MBChB | This project started in June 2018 and closed on 28 June 2019. The Closure Report is now available. |
| MVM131: Migration of 12 applications developed in Biomedical Sciences to central support - Analysis & Strategy | This project started in December 2018 and closed on 28 June 2019. The Closure Report is available to view. |
| MVM133: CMVM Curriculum Mapping Tool - Requirements | This project started in April 2019 and closed on 9th August 2019. The Closure Report is available to view. |
| MVM121: Reporting of Assessment Outcomes for External Bodies | This project started in May 2017 and closed on 22 March 2019. The Closure Report is available to view. |
| MVM127: Upgrading of teaching spaces 2017/18 | This project started in February 2018 and closed on 28 September 2018. The Closure Report is available to view. |
| MVM105: Strategy for the upgrade of our teaching spaces (annual) | This project started in September 2016 and closed on 28 September 2018. The Completion Report is available to view. |
Section Five: Programme Meeting Minutes
|
Date |
Comments |
|---|---|
| 19 August 2019 | Programme Review Monthly Meeting - July 2019 |
| 17 July 2019 | Programme Review Monthly Meeting - June 2019 |
| 11 June 2019 | Programme Review Monthly Meeting - May 2019 |
| 14 May 2019 | Programme Review Monthly Meeting - April 2019 |
| 19 April 2019 | Programme Review Monthly Meeting - February & March 2019 |
| 15 January 2019 | |
| 4 December 2018 | |
| 2 November 2018 | Programme Review Monthly Meeting - October 2018 |
| 27 September 2018 | Programme Review Monthly Meeting - August & September 2018 |