Report for October 2018
- Report Date
- October 2018
![]()
Report by Mark Hay, MVMBUS Programme Manager.
for Jim Nisbet MVMBUS Programme Owner.
CMVM Head of IT (MVM Portfolio Manager) and Catherine Elliot (MVM Portfolio Owner)
Distribution:
- Campus / Deanery meetings.
- College Operations Group (COG) meeting
- Excerpts taken into CSG report.
Section One: Programme Commentary, RAG and Resources Update
Programme Managers Commentary
MVM508 [CMVM Staff and Visitor print consolidation]
Final stages of project phase - delivery to the last site in the bioQuarter is due to take place on or around publication of the report. This gives the opportunity for closure report to be written up.
MVM509 [Implementation of Vet Practice Management System]
Good to see the project has now moved to green and the delivery date is in sight
MVM522 [MVM Business Process Review for SharePoint Delivery]
Ongoing issue concerning access to a sharepoint developer resource. Progress being made in gathering opportunities to take the service forward so there are positive signs of this progressing. Continued lack of the clarity over resourcing has the otential to keep the project red.
MVM523 [Pilot project for WHO's OFF online Staff Leave Management]
Project to be reopened for reports in December.
MVM525 [Procurement of a Vendor Neutral Archiving (VNA) System for the Vet School]
Changes at the root level and costing of the project have determined that the project should be closed and an alternative approach sought. Work in gathering business requirements and procurement can be readily reused.
MVM526 Zhejiang Institute Repository
Excellent progression made and site now operational - Currently in testing phase.
CURRENT PROGRAMME STATUS: RED

Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary | |
|---|---|---|
|
MVM502 |
CMVM College IT communications strategy | This project will be placed under review in Q3 2018 |
| MVM503 | CMVM IT Finance costs portfolio | This project will be placed under review in Q3 2018 |
| MVM507 | Risk, Business Continuity and Disaster Recovery | Linked primarily CIS002 - Oct 2016 - MVM518 - This project will be placed under review in Q3 2018 |
| MVM510 | CMVM Digital literacy staff and student development | This project will be placed under review in Q3 2018 |
| MVM514 | CMVM Bioquarter Infrastructure & IT Services Development | This project will be placed under review in Q3 2018 |
|
MVM516 |
IS - Honours Project Portal move to central resources | Currently at the review stage by Programme Manager - Agreement to move forward - More detailed report for Q4 |
| Active Projects |
|
[MVM508]: CMVM Staff and Visitor print consolidation
Next Steps
|
|
[MVM509] Implementation of Vet Practice Management System RAG is GREEN Achievements in Last Period
Issues
Next Steps
|
|
[MVM522] MVM Business Process Review for SharePoint Delivery RAG is RED Achievements
Issues
Next Steps
|
|
[MVM523]Pilot project for WHO's OFF online Staff Leave Management No report required |
|
[MVM525] Procurement of a Vendor Neutral Archiving (VNA) System for the Vet School RAG is RED Achievements This Period
Issues
Next Steps
|
|
[MVM526] Zhejiang Institute Repository RAG is GREEN Achievements this period
Issues
Next steps
|
Section Four: Closed, Withdrawn or Suspended Projects (For legacy information)
CLOSED
| Project Info | Project Managers Commentary |
|---|---|
| MVM009 | Closed |
| MVM512 | Closed |
| MVM513 | Closed |
| MVM519 | Closed |
| MVM501 | Closed |
WITHDRAWN
| Project Info | Programme Managers comments |
|---|---|
| [MVM511] CMVM College WWW Presence development | Withdrawn |
| [MVM717] CMVM Developing the CMVM Intranet environment | Withdrawn |
| [MVM521] Scientific Linux 7 (SL7) - Psychiatry | Withdrawn |
| [MVM504] CMVM Digitisation of paper records | Withdrawn |
| [MVM506] CMVM Reporting and data intelligence | Withdrawn |
| [MVM503] CMVM Corporate Business Services review | Withdrawn |
SUSPENDED
| Project Info | Programme Managers comments |
|---|---|
| [MVM523] Pilot project for WHO's OFF online Staff Leave Management | Project suspended until December 2019 |