Report for December 2019
- Report Date
- December 2019
Report compiled by Colin Forrest, LTW Programme Manager for Karen Howie (Programme Owner)
Note: MLE007 notes to be added. Believe the project is to be withdrawn.
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Overview
The Programme Board has approved the closure of the Programme and associated projects in October..
The work of the Implementation project has been delivered with the final closure updates to the project website now being prepared and the closure will be approved at the applications weekly quality assurance meeting on Friday the 05th of December.
The work of the Engagement and Evaluation Group (EEG) continues for the next two years. There will be a further series of workshops, to create local guidance for the use of the service. These are planned for Semester 2. Circulation of general student guidance has taken place at the start of term, as planned, with printed copies being distributed in welcome week bags and announcements on Learn. The next meeting for this group will be in December.
An initial draft of a report to summarise the impact of the introduction of the has been created along with an initial review of how far the potential benefits, outlined in the original business case for the Programme, have been met. These reports been presented at the final Programme Board meeting in October. These reports will now be owned by the EEG.
It is proposed that the Academic User Group continues to meet during 2019/20 to support Schools who have yet to make full use of the service and the proposed work to be carried out to implement the service in specialist spaces. The Terms of Reference for the group have been amended to reflect this. The next meeting of the group will also be in Feb 2020.
Overall Programme RAG: Green
Forward Look and RAG

Resource Position

Section Two: Projects Not Started
| None. |
Section Three : Projects in Progress
|
MLE008 Media Hopper Replay Year 4
Discretionary
RAG Status: Green Blue |
Last Month
Notes The project was initiated in at the last Applications QA meeting of 2019. |
|
|
|
|
MLE007 Media Subtitling Phase 2 RAG Status: Red
|
Last Month Report Date: December 2019
Notes This project is currently suspended due to unconfirmed funding arrangements.
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
|
MLE001 Media Service Refresh Project Funded |
Approved at WIS 8/7/16 - Completion Report |
|
MLE002 Lecture Recording Procurement |
http://www.projects.ed.ac.uk/project/mle002/completion-report
|
|
MLE003 Lecture Recording Implementation
|
https://www.projects.ed.ac.uk/project/mle003/closure-report
|
MLE004
Lecture Recording Implementation
https://www.projects.ed.ac.uk/project/mle004/closure-report
MLE005
Lecture Recording Transition
https://secure.projects.ed.ac.uk/project/mle005/closure-report
MVM114
MVM Timetabling and
Room Booking for Medical School
MVM123 Vet School Timetabling and Room Booking Migration
https://secure.projects.ed.ac.uk/project/mvm123/closure-report
| Attachment | Size |
|---|---|
| 52.62 KB | |
| 104.55 KB | |
| 39.52 KB | |
| 83.16 KB |