Report for February 2017

Report Date
February 2017

 

Report compiled by Adam Wadee, IS Apps Programme Manager for Barry Croucher  (Programme Owner)

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

 

Programme Commentary

 

Overall Programme RAG: AMBER

 

Forward Look and RAG

 

Resource Position

 

 

 Section Two: Projects Not Started

 

Project Info Project Manager's Commentary
   
   

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

LMP006 Feeding Visitor data into Alma

D

Milestones

 

 

RAG Status

BLUE

Report by Karen Stirling for February 2017

Achievements in Last Period

  • Finalise SDD documentation
  • Deployment Review sign off completed
  • Project closure documentation completed and reviewed by project team
  • Approval sign off given to close project

Issues

  • Some minor issues investigated and resolved post deployment

Next

  • None

The project current status is now closed

 

LMP008 Resource List software integration with Alma Library Management Platform

D

Milestones

06-Mar-2017

TBC

Contract Starts
07-Mar-2017 TBC Implementation phase starts, if reqd

09-May-2017

TBC

Implementation phase completes, if reqd

06-Jun-2017

TBC

Closure

RAG Status

AMBER

Report by Karen Stirling for February 2017

Achievements in Last Period

  • Preparation for project board meeting
  • Reviewed 'as is' business process further with SMEs to understand new 'to be' process
  • On-going Terms and Conditions negotiations and contractual work
  • An overview of implementation project structure completed
  • Updates to Communication Plan, Project Roles, Implementation Plan
  • Review of project brief underway to update any further details as now covering implementation phase
  • Continual monitoring and action on project risks, risk log updated with new risks associated with implementation phase

Issues

  • As the project will now move into implementation / integration phase a review of the project budget will be required with discussion/ agreement with Programme Manager and Project Sponsor on any additional funding required
  • A slight delay in completion and sign off of Terms & Conditions contract with supplier now expected 6th March
  • Agreement on new additional project milestones for Implementation phase of project

Next Steps

  • Terms and Conditions agreed and contract negotiations completed 
  • Benefits/KPIs review in progress to establish baseline statistics and set targets for the reading list procurement project.
  • Project budget review
  • Sandbox data refresh expected 6th March
  • Agreement to suppliers implementation timescales and updated milestones
  • Kick off key integration activities, training

The project status is AMBER due to slight delay in completion and sign off of Terms & Conditions contract with supplier

 

Section Four: Closed or Withdrawn Projects

 

 

Project Info Project Managers Commentary

LMP001

New Library Management Platform Procurement

Discretionary

Report By Karen Stirling

This project was closed 6th March 2015

Completion Report

LMP002 Implementation of a next generation Library Services platform

Discretionary

Report By Karen Stirling

This project was closed 11th September 2015

Completion Report

LMP003 LMP - EASE Integration

Discretionary

Report By Karen Stirling

This project was closed 30th July 2015

Completion Report

LMP004

LMP - IDM Integration

Discretionary

Report By Karen Stirling

This project was closed 3rd September 2015

Completion Report

LMP005

LMP - Integration with Finance

Discretionary

Report By Karen Stirling

This project was closed 30th October 2015

Completion Report

LMP007 Online Fine Payments

Discretionary

Report by Morna Findlay

Project was closed on 2nd September 2016

Completion Report

LMP006

Feeding Visitor data into Alma

Discretionary

Report By Karen Stirling

This project was closed 24th February 2017

Completion Report

 

 

 

 

 

AttachmentSize
Image icon lmp_rag_feb-17.jpg40.95 KB
Image icon lmp_resources_feb-17.jpg110.63 KB