Report for November 2016

Report Date
November 2016

 

Report compiled by Adam Wadee, IS Apps Programme Manager for Barry Croucher  (Programme Owner)

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

 

Programme Commentary

 

Overall Programme RAG: GREEN

 

Forward Look and RAG

 

Resource Position

 

 

 Section Two: Projects Not Started

 

Project Info Project Manager's Commentary
   
   

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

LMP006 Feeding Visitor data into Alma

D

Milestones

 

09-Dec-16 Acceptance complete
10-Jan-17 Deployment complete
26-Jan-17 Deployment Review
31-Jan-17 Closure

 

RAG Status

GREEN

Report by Karen Stirling for November 2016

Achievements in Last Period

  • Integration testing completed
  • Change Based Feed UAT in progress
  • Self Reg UI UAT completed
  • VRS Library Patron UAT in progress, including card test and door access
  • VRS Official Visitor UAT completed, review of outstanding JIRAs to be completed
  • Deployment checklist in progress
  • EQIA completed and reviewed by Viki Galt
  • Self Reg UI has been tested for accessibility
  • Implementation roll out steps for live deployment drafted

Issues

  • Confirmation that library membership UUN number can be used – Service Manager has confirmed use of m1xxxxx
  • DOB data issue on VRS / IDM this is an existing issue on Live VRS
  • Business team have requested changes to Self Reg UI  following completion of testing this is to  accommodate a change  of scope to process for NHS Lothian staff ,an assessment of UI change is required  for effort and introduces an associated risk to completion of UAT as developer is due to go on leave from 9th Dec
  • Request from Business team for the deployment to live be moved to week commencing 23rd January

Next

  • Complete Acceptance sign off
  • Production handover
  • Deployment Checklist
  • Preparation work for business processes and deployment in advance of festive break

     

The project current status is GREEN

 

LMP008 Resource List software integration with Alma Library Management Platform

D

Milestones

23-Dec-2016 Evaluation Phase Ends
11-Jan-2017 Contract Recommendation Award
02-Feb-2017 Contract Starts
03-Feb-2017 Implementation phase starts, if reqd
28-Apr-2017 Implementation phase completes, if reqd
31-May-2017 Closure

RAG Status

GREEN

Report by Karen Stirling for November 2016

Achievements in Last Period

  • Clarifications being passed to Procurement and fed back to potential suppliers
  • Return of ITT from prospective suppliers on 4th November
  • IS Apps Business Analyst initial review completed of existing processes aligned to Reading List
  • Project Board meeting held on 16th November to provide latest update and project progress
  • Preparations for supplier demos expected to take place early December

Issues

  • Mandatories and future development planned for supplier (1) highlight associated risks and raise to project board on 14th December

Next Steps

  • Complete evaluation consensus scores
  • EQIA to be drafted
  • Update project board of progress 14th December

The project current status is GREEN

Section Four: Closed or Withdrawn Projects

 

 

Project Info Project Managers Commentary

LMP001

New Library Management Platform Procurement

Discretionary

Report By Karen Stirling

This project was closed 6th March 2015

Completion Report

LMP002 Implementation of a next generation Library Services platform

Discretionary

Report By Karen Stirling

This project was closed 11th September 2015

Completion Report

LMP003 LMP - EASE Integration

Discretionary

Report By Karen Stirling

This project was closed 30th July 2015

Completion Report

LMP004

LMP - IDM Integration

Discretionary

Report By Karen Stirling

This project was closed 3rd September 2015

Completion Report

LMP005

LMP - Integration with Finance

Discretionary

Report By Karen Stirling

This project was closed 30th October 2015

Completion Report

LMP007 Online Fine Payments

Discretionary

Report by Morna Findlay

Project was closed on 2nd September 2016

Completion Report

 

 

 

 

 

AttachmentSize
Image icon lmp_rag_nov-16.jpg45.44 KB
Image icon lmp_resources_nov-16.jpg115.76 KB