- Report Date
- July 2016
Report compiled by Adam Wadee, IS Apps Programme Manager for Barry Croucher (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
Overall Programme RAG: AMBER
Forward Look and RAG July 2016

Resource Position to end July 2016

Section Two: Projects Not Started
Project Info | Project Manager's Commentary |
| |
| |
Section Three: Projects in Progress
Project Info | Project Manager's Commentary |
LMP006
Feeding Visitor data into Alma D Milestones RAG Status AMBER | Report by Karen Stirling for July 2016 Achievements in Last Period - Ongoing Development builds for MicroService, VRS Changes and Self Reg - UI being built in parallel
- Change Based Feed test plan documented ready for review with Library / Helpdesk team and confirm testing completion date and deployment date
- Requirements Traceability Matrix created to map requirements to SDS and Test plan and inform requirements which will not be developed
- Initial setup on all the appsutil servers now completed for the microsrv user
- Library IDM Feed TADs updated
- Completed OAuth2 installation for Micro Service
Issues - Additional funding to be sought for 16/17 project activity - Programme Manager to confirm if funding available from 16/17 LMP Programme
- Peer testing for change based delayed due to availability of resource expected to deploy to test week commencing 8th Aug
- Developer resource conflicted to TEL032 project for Collaborate Learn issues to be resolved by 21st July for Live Deployment – this has delayed build activity by 10 days therefore peer testing of VRS will commence 8th Aug and Self Reg UI 15th August
Next - Server builds to be completed
- Build peer testing and review sign off to be completed
- Confirm business contacts to review Self Reg UI
- Work with business areas to complete test plans in advance of development work being completed - initial testing workshop involving IS Apps scheduled for 3rd August
- Complete testing for Change Based Feed and Bulk Feed
- Complete EQIA
The project current status is AMBER due to budget constraints for 16/17 and delay to build completion |
LMP007
Online Fine Payments D MilestonesProject StatusGREEN | Report by Morna Findlay for July 2016 Achievements this period- User acceptance testing signed off
- Equalities Impact assessment completed
- Documentation for users and support staff completed
- Acceptance review successful
- Delivery achieved
IssuesNone Next Steps - Deployment sign off review to be held
- Closure review to be held
- Project to close
|
LMP008
Resource List software integration with Alma Library Management Platform D Milestones RAG Status GREEN | Report by Karen Stirling for July 2016 Achievements in Last Period - The key elements of this project are the procurement of a Resource List software working with Library and University Collections and Procurement to gather requirements and evaluate an ITT tender submission, and the integration of the awarded supplier to link to Library Management Platform
- Project initated and project manager assigned
- Initial fact finding meeting held with Business Lead
- Project website created
- Initial demos presented to Library representatives week commencing 25th July by 4 supplier following PIN having been issued out in May
Issues - The project budget will require a full assessment as original annual planning project submitted was only to cover integration element further funding will be required to cover procurement element as well and has been raised with Business Lead
Next Steps The project status is GREEN |
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
LMP001 New Library Management Platform Procurement Discretionary | Report By Karen Stirling This project was closed 6th March 2015 Completion Report |
LMP002
Implementation of a next generation Library Services platform Discretionary | Report By Karen Stirling This project was closed 11th September 2015 Completion Report |
LMP003
LMP - EASE Integration Discretionary | Report By Karen Stirling This project was closed 30th July 2015 Completion Report |
LMP004 LMP - IDM Integration Discretionary | Report By Karen Stirling This project was closed 3rd September 2015 Completion Report |
LMP005 LMP - Integration with Finance Discretionary | Report By Karen Stirling This project was closed 30th October 2015 Completion Report |