Report for June 2016

Report Date
June 2016
 

Report compiled by Adam Wadee, IS Apps Programme Manager for Barry Croucher  (Programme Owner)

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

 

Overall Programme RAG: AMBER

 

 

 Section Two: Projects Not Started

 

 

Project InfoProject Manager's Commentary
  
  

 

Section Three: Projects in Progress

 

Project InfoProject Manager's Commentary

LMP006 Feeding Visitor data into Alma

D

Milestones

 

29-Jul-2016Build complete
19-Aug-2016Integration testing complete
21-Oct-2016Acceptance complete
28-Oct-2016Deployment complete
11-Nov-2016Deployment Review
18-Nov-2016Closure

 

RAG Status

AMBER

Report by Karen Stirling for June 2016

Achievements in Last Period

  • All System Design Specifications have been reviewed by project team
  • Development build for Change Based Feed / Bulk Feed complete and can now be deployed to test
  • Development builds for MicroService, VRS Changes and Self Reg - UI being built in parallel

Issues

  • Additional funding to be sought for 16/17 project activity

Next

  • VRS and Library IDM Feed TADs to be updated
  • Server builds to be completed
  • Library and helpdesk to finalise wording for errors messages, UI and emails to allow build work to complete
  • Build peer testing to be completed
  • Work with business areas to complete test plans in advance of development work being completed
  • Complete testing for Change Based Feed and Bulk Feed
  • Complete EQIA

The project current status is AMBER due to budget constraints for 16/17 this is being sought with involvement from Project Sponsor

LMP007 Online Fine Payments

D

 

Milestones

11-July-2016Acceptance Review
25-July-2016Delivery
29-Aug-2016Closure

Project Status

The project status is AMBER as the delivery date has been pushed back by two weeks.

Project Status

 

AMBER

Report by Morna Findlay for June 2016

 

Achievements this period

  • New project milestones agreed and resources assigned to new dates
  • MyEd changes delivered into TEST
  • pcounter changes signed off in TEST and delivered into LIVE
  • User accepance testing in progress

 

Issues

None

 

Next Steps

 

  • Complete user acceptance testing
  • Sign off new user documentation for online fine payments
  • Sign off business process changes re standard fine for replacement costs
  • Sign off business process changes re standard fine for refunds
  • Sign off communications plan for changes to print credit and payments of fines
  • Complete EqIA

 

The project status is AMBER as the delivery date has been pushed back by two weeks.

Section Four: Closed or Withdrawn Projects

 

 

Project InfoProject Managers Commentary

LMP001

New Library Management Platform Procurement

Discretionary

Report By Karen Stirling

This project was closed 6th March 2015

Completion Report

LMP002 Implementation of a next generation Library Services platform

Discretionary

Report By Karen Stirling

This project was closed 11th September 2015

Completion Report

LMP003 LMP - EASE Integration

Discretionary

Report By Karen Stirling

This project was closed 30th July 2015

Completion Report

LMP004

LMP - IDM Integration

Discretionary

Report By Karen Stirling

This project was closed 3rd September 2015

Completion Report

LMP005

LMP - Integration with Finance

Discretionary

Report By Karen Stirling

This project was closed 30th October 2015

Completion Report