Report for May 2016

Report Date
May 2016
 

Report compiled by Adam Wadee, IS Apps Programme Manager for Barry Croucher  (Programme Owner)

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

 

Overall Programme RAG: AMBER

 

 

 Section Two: Projects Not Started

 

 

Project InfoProject Manager's Commentary
  
  

 

Section Three: Projects in Progress

 

Project InfoProject Manager's Commentary

LMP006 Feeding Visitor data into Alma

D

Milestones

 

03-Jun-2016SDS - Change Based Feed and Bulk Feed Split by Type
03-Jun-2016SDS - Library Info Microservice
08-Jun-2016SDS - VRS Changes
29-Jun-2016SDS - Self- Registration UI
29-Jul-2016Build complete
19-Aug-2016Integration testing complete
21-Oct-2016Acceptance complete
28-Oct-2016Deployment complete
11-Nov-2016Deployment Review
18-Nov-2016Closure

 

RAG Status

AMBER

Report by Karen Stirling for May 2016

Achievements in Last Period

  • Final BRD version signed off by all areas
  • Application & Data Architecture document sign off requested following BRD completion (3 oustanding sign offs being chased)
  • Re-estimation provided by Development team
  • Agreement for Design to be completed in 4 phases
    • SDS has been produced for Change Based Feed and Bulk Feed Split by Type (sign off outstanding from L&UC presentative), development work completed and will be deployed to test on confirmation from L&UC and available to test
    • SDS has been produced for Library Info MicroService and issued for reviewed (sign off from IS Applications Developers and L&UC presentative required)
    • SDS for VRS Changes
    • SDS for Self Registration UI
  • Revised milestones have been agreed with Business Lead and Project Sponsor
  • Self - Registration Form Question Sets reviewed by Helpdesk team representatives
  • Senior Supplier role has agreed for project - this is to be held by both Lorraine Brown from Service Management and Adam Wadee Programme Manager - regular meetings now scheduled

Issues

  • Re-estimation has been reviewed with Project Sponsor, Programme Manager and Programme Owner/ Business lead and confirmed project to continue and additional funding being sought

Next

  • SDS for VRS Changes - documentation and review scheduled for 8th June
  • SDS for Self Registration UI - documentation scheduled for 29th June
  • devleopment work will be undertaken in parallel for these elements to keep this activity on schedule
  • Work with business areas to complete test plans in advance of development work being completed

 

The project current status is AMBER due to budget constraints for 16/17 this is being sought with involvement from Project Sponsor

LMP007 Online Fine Payments

D

Milestones

27-Jun-2016Acceptance Review
11-Jul-2016Delivery
25-Jul-2016Closure

Project Status

RAG Status

AMBER

Report by Morna Findlay for May 2016

Achievements this period

New project milestones agreed

Scope change agreed to update pcounter link to WPM

Update to pcounter delivered to TEST  and WPM updated in TEST for acceptance testing

pcounter testing under way

 

Issues

Delivery of MyEd changes into TEST delayed due to issue caused by WEB009 project

Signoff required for pcounter changes from business

 

Next Steps

  • Signoff pcounter changes in TEST and deliver into LIVE
  • Complete user acceptance testing

 

Project Status

The project status is AMBER due to the unresolved MyEd issue as the WEB009 team has not given a deadline to fix this issue.

Section Four: Closed or Withdrawn Projects

 

 

Project InfoProject Managers Commentary

LMP001

New Library Management Platform Procurement

Discretionary

Report By Karen Stirling

This project was closed 6th March 2015

Completion Report

LMP002 Implementation of a next generation Library Services platform

Discretionary

Report By Karen Stirling

This project was closed 11th September 2015

Completion Report

LMP003 LMP - EASE Integration

Discretionary

Report By Karen Stirling

This project was closed 30th July 2015

Completion Report

LMP004

LMP - IDM Integration

Discretionary

Report By Karen Stirling

This project was closed 3rd September 2015

Completion Report

LMP005

LMP - Integration with Finance

Discretionary

Report By Karen Stirling

This project was closed 30th October 2015

Completion Report