Report for April 2016

Report Date
April 2016
 

Report compiled by Adam Wadee, IS Apps Programme Manager for Barry Croucher  (Programme Owner)

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

 

Overall Programme RAG: AMBER

 

 

 Section Two: Projects Not Started

 

 

Project InfoProject Manager's Commentary
  
  

 

Section Three: Projects in Progress

 

Project InfoProject Manager's Commentary

LMP006 Feeding Visitor data into Alma

D

Milestones

13-May-2016Business Analysis and ADA complete
03-Jun-2016Design complete (tbc)
29-Jul-2016Build complete (tbc)
19-Aug-2016Integration testing complete (tbc)
30-Sep-2016Acceptance complete (tbc)
07-Oct-2016Deployment complete (tbc)
21-Oct-2016Deployment Review (tbc)
28-Oct-2016Closure (tbc)

RAG Status

RED

Report by Karen Stirling for April 2016

Achievements in Last Period

  • Revised 'to be' process flows produced and reviewed
  • Updated BRD document has been issued out for review by Library and helpdesk teams and sign off now being requested
  • Application & Data Architecture document reviewed and re-estimate for IS Apps effort provided
  • Card mock up created by LTW Graphics team for Library Committe meeting being held in May

Issues

  • Due to review and update of BRD and process maps and redrafting of Application and Data Architecture documentation has had a knock on effect to budget effort and timescales for project delivery
  • Revised Project milestones have been proposed to business team however due to key business times over Sept and Oct these have been extended, dates still to be confirmed
  • Re-estimation of effort following ADA and BRD have estimated project at a higher costs than is currently available additional funding will have to be sought for 16/17 if project has to continue or reassessment of priority requirements to be undertaken
  • Due to delays developer resource require work to be provided or team will be reallocated, request for BRD elements that are separate to Self registraion UI activity that can be completed independently of this to keep developer resource occupied whilst BRD sign off achieved.

Next

  • Finalise BRD and achieve sign off
  • ADA achieve sign off
  • Complete SDS documentation
  • Confirm revised milestones and agree new aligned budget

 

The project current status is RED due to delay to BRD sign off due to review and redrafting of requirements also impact on milestones and resource effort required to complete project, these have to be agreed with Project Sponsor / Business Lead and Programme Manager

LMP007 Online Fine Payments

D

Milestones

20-May-2016Acceptance Review
20-Jun-2016Delivery
11-Jul-2016Closure

Project Status

RAG Status

AMBER

Report by Morna Findlay for April 2016

 

Achievements this period

  • MyEd  peer testing completed
  • Issue  LMP007-1 resolved
  • ALMA - WPM testing completed in DEV/Sandbox
  • Build review achieved
  • Project estimate revised and  milestones reviewed

 

Issues

  • Existing issue with WPM setup identified which must be resolved before LMP007 can proceed: https://www.jira.is.ed.ac.uk/browse/LMP007-5
  • Adressing this issue may impact the current budget as the work to get online print credit working with the required changes may have to be funded by LMP007

 

Next Steps

  • Work with FIN110 and SMI014 to identify when LMP007-5 can be addressed
  • Agree new milestones for LMP007-5 as existing milestones will not now be achievable
  • Commence user acceptance testing

 

Project Status

The project status is AMBER as there is a plan to address the LMP007-5 issue but the timeline is not yet agreed

Section Four: Closed or Withdrawn Projects

 

 

Project InfoProject Managers Commentary

LMP001

New Library Management Platform Procurement

Discretionary

Report By Karen Stirling

This project was closed 6th March 2015

Completion Report

LMP002 Implementation of a next generation Library Services platform

Discretionary

Report By Karen Stirling

This project was closed 11th September 2015

Completion Report

LMP003 LMP - EASE Integration

Discretionary

Report By Karen Stirling

This project was closed 30th July 2015

Completion Report

LMP004

LMP - IDM Integration

Discretionary

Report By Karen Stirling

This project was closed 3rd September 2015

Completion Report

LMP005

LMP - Integration with Finance

Discretionary

Report By Karen Stirling

This project was closed 30th October 2015

Completion Report