Report for February 2016

Report Date
February 2016
 

Report compiled by Adam Wadee, IS Apps Programme Manager for Barry Croucher  (Programme Owner)

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

 

Overall Programme RAG: GREEN

 

 

 

 Section Two: Projects Not Started

 

 

Project InfoProject Manager's Commentary
  
  

 

Section Three: Projects in Progress

 

Project InfoProject Manager's Commentary

LMP006 Feeding Visitor data into Alma

D

Milestones

11-Mar-2016Business Analysis
18-Mar-2016ADA & Design
29-Apr-2016 (tbc)Build
20-May-2016 (tbc)Integration
24-Jun-2016 (tbc)Acceptance
07-Jul-2016 (tbc)Delivery
22-Jul-2016 (tbc)Deployment Review
29-Jul-2016 (tbc)Closure

RAG Status

AMBER

Report by Karen Stirling for February 2016

Achievements in Last Period

  • Walkthrough of processes held with VRS Service Owner, Project Sponsor and Programme Owner / Manager
  • BRD workshop to finalise requirements further activity needed before final sign off achieved
  • Card Mock ups completed
  • Visitor process timelines created to aid discussions in increasing frequency of CRON jobs for VRS to CARD and CARD to Access Management System
  • Initial discussion with Business lead regarding UAT responsibilities, Training and Communication plans

Issues

  • A point has been raised around processes for Alumni and how this fits into 'to be' processes therefore a meeting has been arranged for 25th February. Business Requirements documentation to be finalised on the completion of these discussions.
  • Review milestones due to additional work being required for Bussiness Requirements Document

Next

  • Finalise BRD and achieve sign off
  • Complete and gain approval for ADA in parallel with SDS (design document)

 

The project current status is AMBER due additional work required on Business Requirements Documentation

LMP007 Online Fine Payments

D

Milestones

3-Mar-2016Design Review
15-Apr-2016Build Review
20-May-2016Acceptance Review
10-Jun-2016Delivery
24-Jun-2016Closure

Project Status

RAG Status

GREEN

Report by Morna Findlay for February 2016

 

Achievements this period

 

  • Business requirements document signed off
  • Existing project estimate and milestones confirmed - to be reviewed at end of design stage
  • Probable solution identified
  • Testing of probable solution under way
  • System design document drafted and circulated

 

Issues

  • none at this time

 

Next Steps

  • Sign off system design
  • Re-estimate project and confirm milestones
  • Build stage to commence

 

Section Four: Closed or Withdrawn Projects

 

 

Project InfoProject Managers Commentary

LMP001

New Library Management Platform Procurement

Discretionary

Report By Karen Stirling

This project was closed 6th March 2015

Completion Report

LMP002 Implementation of a next generation Library Services platform

Discretionary

Report By Karen Stirling

This project was closed 11th September 2015

Completion Report

LMP003 LMP - EASE Integration

Discretionary

Report By Karen Stirling

This project was closed 30th July 2015

Completion Report

LMP004

LMP - IDM Integration

Discretionary

Report By Karen Stirling

This project was closed 3rd September 2015

Completion Report

LMP005

LMP - Integration with Finance

Discretionary

Report By Karen Stirling

This project was closed 30th October 2015

Completion Report