Report for January 2016

Report Date
January 2016
 

Report compiled by Adam Wadee, IS Apps Programme Manager for Barry Croucher  (Programme Owner)

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

At mid-year review stage the LMP Programme is being reported as GREEN. Both LMP006 and LMP007 are in progress and are at similar stages, coming to the end of the analysis phases.  Both are still on target to deliver according to plan.

 

Overall Programme RAG: GREEN

 

 

 

 Section Two: Projects Not Started

 

 

Project InfoProject Manager's Commentary
  
  

 

Section Three: Projects in Progress

 

Project InfoProject Manager's Commentary

LMP006 Feeding Visitor data into Alma

D

Milestones

12-Feb-2016Business Analysis
04-Mar-2016ADA & Design
29-Apr-2016 (tbc)Build
20-May-2016 (tbc)Integration
24-Jun-2016 (tbc)Acceptance
07-Jul-2016 (tbc)Delivery
22-Jul-2016 (tbc)Deployment Review
29-Jul-2016 (tbc)Closure

RAG Status

GREEN

Report by Karen Stirling for January 2016

Achievements in Last Period

  • Workshop held on 7th January with Library and Helpdesk representatives together with VRS Service Manager to review 'to be‘ processes
  • 'To be' processes documented and issued out for further review
  • Identified Door Access contact for cards within IS ITI as an additional stakeholder
  • Initial draft of business requirements produced and updated following review of' to be' processes from discussions with business areas.
  • Architecture document initial framework created.

Issues

  • Original plan for developer to complete ADA alongside BRD however not enough detail available for developer to complete prior to his annual leave. The ADA can be produced in parallel with the SDS on their return. Review dates for BRD completion.
  • Risk highlighted that a key stakeholder will be on extended leave whilst Architecture and System design is expected to be reviewed and signed off. Meeting to be arranged to review and identify what plans can be put in place to mitigate the risk or where milestones will have to be changed and agreed with project sponsor.

Next

  • Arrange walk through with VRS Service Owner, Project Sponsor and Programme Owner / Manager
  • Finalise BRD and achieve sign off
  • Draft UAT, Training and Communication plans
  • Complete and gain approval for ADA in parallel with SDS (design document)

 

The project status is currently GREEN

LMP007 Online Fine Payments

D

Milestones

04-Feb-2016Analysis Review - Sign off Business Requirements
26-Feb-2016Design Review
15-Apr-2016Build Review
20-May-2016Acceptance Review
10-Jun-2016Delivery
24-Jun-2016Closure

Project Status

RAG Status

GREEN

Report for January 2016

Achievements this period

  • Draft Business requirements document circulated
  • New milestone for analysis review agreed 

 

Issues

  • extra time required for completion of BRD

 

Next Steps

  • Complete analysis of business requirements
  • Re-estimate project and confirm milestones
  • Secure resources for remainder of project

 

Section Four: Closed or Withdrawn Projects

 

 

Project InfoProject Managers Commentary

LMP001

New Library Management Platform Procurement

Discretionary

Report By Karen Stirling

This project was closed 6th March 2015

Completion Report

LMP002 Implementation of a next generation Library Services platform

Discretionary

Report By Karen Stirling

This project was closed 11th September 2015

Completion Report

LMP003 LMP - EASE Integration

Discretionary

Report By Karen Stirling

This project was closed 30th July 2015

Completion Report

LMP004

LMP - IDM Integration

Discretionary

Report By Karen Stirling

This project was closed 3rd September 2015

Completion Report

LMP005

LMP - Integration with Finance

Discretionary

Report By Karen Stirling

This project was closed 30th October 2015

Completion Report