Report for January 2016
- Report Date
- January 2016
Report compiled by Adam Wadee, IS Apps Programme Manager for Barry Croucher (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
At mid-year review stage the LMP Programme is being reported as GREEN. Both LMP006 and LMP007 are in progress and are at similar stages, coming to the end of the analysis phases. Both are still on target to deliver according to plan.
Overall Programme RAG: GREEN
Section Two: Projects Not Started
Project Info | Project Manager's Commentary |
Section Three: Projects in Progress
Project Info | Project Manager's Commentary | ||||||||||||||||
LMP006 Feeding Visitor data into Alma D Milestones
RAG Status GREEN | Report by Karen Stirling for January 2016 Achievements in Last Period
Issues
Next
The project status is currently GREEN | ||||||||||||||||
LMP007 Online Fine Payments D Milestones
Project StatusRAG Status GREEN | Report for January 2016 Achievements this period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
LMP001 New Library Management Platform Procurement Discretionary | Report By Karen Stirling This project was closed 6th March 2015 |
LMP002 Implementation of a next generation Library Services platform Discretionary | Report By Karen Stirling This project was closed 11th September 2015 |
LMP003 LMP - EASE Integration Discretionary | Report By Karen Stirling This project was closed 30th July 2015 |
LMP004 LMP - IDM Integration Discretionary | Report By Karen Stirling This project was closed 3rd September 2015 |
LMP005 LMP - Integration with Finance Discretionary | Report By Karen Stirling This project was closed 30th October 2015 |