Report for May 2013
- Report Date
- May 2013
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
During this period, work has continued on all active projects
The IS Application resourcing over the period throughout May can be summarised as follows:
- May 2013 91 days which equates to a monthly burn rate of 190%
- The overall burn rate for the year is 108%
The programme is now no longer in budget as an additional 30 days as are required for ITS100 Implement New Database Tier with the balance row in April showing 25 days available. In additional to this ITS095 SOA Upgrade will also required more days to complete this year. The number of days will become clearer in the early part of June.
RAG Status

Resources

Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | |||||||||||||||||||||
ITS095 (AP12-031) Upgrade of Oracle SOA Suite
Category:Discretionary Milestones
RAG Status RED | Report by Stevie Conlon for May 2013 Achievements This Period
Issues
Next steps
The project has been marked as Red as milestones and budget have yet to be agreed.
| |||||||||||||||||||||
ITS100 (AP23-008) Implement New Database Tier Category: Compliance Milestones
RAG Status AMBER Project status has been set at AMBER because revised milestones and effort have not yet been approved by WIS (submitted 06/06) | Report by David Watters for May 2013 Achievements in Last Period
| |||||||||||||||||||||
ITS101 (AP23-009) SAN Migration Category: Compliance Milestones
RAG Status AMBER | Report by Karen Stirling for May 2013 Achievements in Last Period
Issues
Next Steps
| |||||||||||||||||||||
ITS102 (AP23-010) Card System Migration Category: Compliance Milestones
RAG Status GREEN | Report by Karen Stirling for May 2013
Achievements this Period
Issues Initial build completed to plan however peer testing problems with timeouts on batch prints identified – load balancer / cold fusion problems investigated by DevTech as inconsistent test results, this impacted the completion of build review and knock on effect to integration testing and UAT commencement. Deployment date to be moved to a mid week date - 18/19 June Next Steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
Project Code: AP12-907 Project Title: New SAN Infrastructure Procurement
Discretionary | Report by Andrew Stewart This project was closed on 24-08-12 Please see the Completion Report for further information
|
Project Code: AP12-904 Project Title: Windows 7 Managed Desktop Rollout
Compliance | Report by Andrew Stewart This report was closed on 14-09-12 Please see the Completion Report for further information |
Project Code ColdFusion Upgrade - EVES
Category:Compliance | Report by David Watters This project was closed on 28-09-12 Please see the Completion Report for further information |
Project Code: AP12-008 Project Title: Oracle 11g Database Estate Upgrade | Project was withdrawn at WIS on 28-01-13 |
Project Code: AP12-027 Project Title: Software Licences and Agreements Management | Project submitted for withdrawal at WIS on 15-02-13 |
