Report for September 2019
- Report Date
- September 2019
IS Applications Infrastructure Programme Report for Programme Owner Stefan Kaempf
Section One: Programme Commentary, RAG and Resources Update
Overall Programme RAG: GREEN
All projects planned, start dates set, continuing projects as planned or allocated budget for unplanned. Requests for project managers made and PM's have been assigned to all projects bar one.
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary | |
|
||
AP90-013 INF149 Move non IS based Oracle databases to VMs and stretched cluster | David Watters PM, starting Nov | |
AP90-014 INF150 AppsUtil Centos EOL build Centos 7 version | Anne Mathison PM, Started | |
AP90-015 INF154 Annual Upgrade of Development Tools + frameworks | Anne Mathison PM, Started | |
AP90-015 INF153 ASTA Upgrade | Karen Stirling PM, starting Oct | |
AP90-016 INF151 Encryption at Rest Rollout (Multiyear 1 of 2) | Sue Woodger PM, starting Nov | |
AP89-104 INF152 Coldfusion Upgrades - CF11 and Hosting | Sue Woodger PM, started | |
AP90-061 INF147 Mitigate Security Vulnerability for high privilege users | Adam Wadee assigned, starting Oct | |
AP90-062 INF148 Patching process for application components - Implementation (2 year project) | Starting Feb 2020 | |
AP90-063 INF146 Migration of SVN to GIT | Karen Stirling PM, starting Nov | |
AP90-100 INF155 Annual Infrastructure Rationalisation Decommissioning | David Watters PM, started | |
Section Three: Projects in Progress
Project Info |
Project Manager's Commentary |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||
CF10 Updates
Milestones
These milestones will be re-planned once patches are available and we have confidence in re-planned dates
RAG Status AMBER |
Report by Sue Woodger for September 2019Achievements in last period
Issues
Next Steps
Project is Amber Description: Project is Amber as milestones have passed and we have no confidence in future dates until Adobe confirm patches are available. Impact: Project again delayed Plan: Re-plan once patches are made available |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Move IS based Oracle databases to VMs and stretched cluster Milestones
RAG Status: GREEN
|
Report by David Watters for September 2019Achievements
Issues
Next steps
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||
INF143 - MySQL Environment Migration Milestones
RAG Status GREEN |
Report by Maurice Franceschi for September 2019Summary - Scope and Objective ChangeOriginal plan and of this project was to move to a virtualised environments and to use MariaDB in preference to MySQL. As a by product of the project, the University would stop using MySQL and avoid a £27,000 licence maintenance renewal. The project scope did not include decommissioning of the MySQL environments. However, as of 30th July 2019 clarification has been received from Oracle, the licence owner of MySQL, that to avoid the licence renewal liability, all MySQL environments must be decommissioned. This must be accomplished by Mid October 2019. The impact of this objective change increases pressure on the project to deliver the full decommissioning . A change request has been raised to increase the overall project priority from Higher to Highest. A further change request needs to be documented to add a number of additional deliverables including;
Other contingency mitigation options have been considered but no recommendation has been put forward. These include;
The risk of not achieving the 25th October has been reduced by the team's decision to migrate to Maria DB on the current physical server, with the move to VM as a separate second stage of the project. Achievements in Last Period
Issues/Risk
Next Steps
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||
INF150 - AP90-014 AppsUtil OS EOL build Centos 7 version
Milestones
RAG Status GREEN
|
Report by Anne Mathison for September 2019Achievements
Issues
Next Steps
Green RAG status this month |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||
INF152 ColdFusion Upgrades CF11
Milestones
These milestones have still to be approved by project team for project brief
RAG Status GREEN |
Report by Sue Woodger for September 2019Achievements in last period
Issues
Next Steps
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||
INF154 - AP90-015 Annual Upgrade of Development Tools + frameworks 19/20
Milestones
RAG Status GREEN |
Report by Anne Mathison for September 2019Achievements
Issues
Next Steps
Green RAG status this month |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||
INF155: Annual Infrastructure Rationalisation Decommissioning Milestones
RAG Status GREEN
|
Report by David Watters for September 2019Achievements
Issues
Next steps
|
Project Info | Project Managers Commentary |
INF140 Middleware patching process |
Project Closed 2-Aug-2012 |
INF145 Protecting Data in the Enterprise Data Warehouse (EDW) |
Project Closed 8-Aug-2019 |
Attachment | Size |
---|---|
![]() | 320.24 KB |
![]() | 258.31 KB |