Report for July 2019
- Report Date
- July 2019
IS Applications Infrastructure Programme Report for Programme Owner Stefan Kaempf
Section One: Programme Commentary, RAG and Resources Update
Overall Programme RAG: RED
All projects planned, start dates set, continuing projects as planned or allocated budget for unplanned. Requests for project managers made and PM's have been assigned to all projects. Additional projects INF144 and INF145 added to programme.
However, an increasing number of projects are reporting lack of resource and conflict of resource - if there are no resolution in May 2019 then programme will have to re-consider viability of delivering many of its benefits in 18/19 (Risk raised)
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
Section Three: Projects in Progress
Project Info |
Project Manager's Commentary |
||||||||||||||||||||||||||||||||||||
CF10 Updates
Milestones
RAG Status GREEN |
Report by Sue Woodger for July 2019Achievements in last period
Issues
Next Steps
Project is GREEN again as resourcing has been confirmed and revised milestone dates agreed. |
||||||||||||||||||||||||||||||||||||
INF139 Annual Upgrades of Development Tools + frameworks 18/19 (18-19 Project) AP89-018 Milestones No further milestones RAG Status BLUE |
Report by Anne Mathison for July 2019AchievementsPMP
Oracle Grid
General
Issues
Next Steps
BLUE RAG status
|
||||||||||||||||||||||||||||||||||||
INF140 - Middleware Patching Process Milestones
RAG Status AMBER |
Report by Karen Stirling for July 2019Achievements in Last Period
Issues
Next Steps
This project is AMBER as closure approval via Internal Application process not approved, review outstanding points with Development Services SOM for them to confirm closure and resubmit.
|
||||||||||||||||||||||||||||||||||||
Move IS based Oracle databases to VMs and stretched cluster Milestones
RAG Status: GREEN
|
Report by David Watters for July 2019Achievements
Issues
Next steps
|
||||||||||||||||||||||||||||||||||||
INF143 - MySQL Environment Migration Milestones To Be Replanned
RAG Status RED |
Report by Maurice Franceschi for July 2019
Achievements in Last Period
The original plan and of this project was to move to a virtualised environments and to use MariaDB in preference to MySQL. As a by product of the project, the University would stop using MySQL and avoid a £27000 licence maintenance renewal. The project scope did not include decommissioning of the MySQL environments. However, as of 30th July 2019 clarification has been received from Oracle, the licence owner of MySQL, that to avoid the licence renewal liability, all MySQL environments must be decommissioned. This must be accomplished by Mid October 2019. The impact of this objective change increases pressure on the project to deliver the full decommissioning . A change request has been raised to increase the overall project priority from Higher to Highest. A further change request needs to be documented to add a number of additional deliverables including;
Other contingency mitigation options have been considered but no recommendation has been put forward. These include;
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||
Protecting Data in the EDW Milestones
RAG Status Green |
Report by Kevin Hone for July 2019
Achievements
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
INF127 (17-18 Project) LAMP / WIMP Platform Upgrade |
Project Closed 12-Oct-2018 |
INF136 Annual Business Technology End of Life Analysis | Withdrawn Feb 2019 |
INF144 Encryption at Rest - Analysis |
Project Closed 3-May-2019 |
INF121 - Migrate core databases to Oracle 12c |
Project Closed 3-May-2019 |
INF129 - Wiki Database Resilience Improvement |
Project Closed 3-May-2019 |
INF137 - Annual Infrastructure Rationalisation Decommissioning |
Project Closed 14-June-2019 |
INF139 Annual Upgrades of Development Tools + frameworks 18/19 (18-19 Project) |
Project Closed 29-July-2019 |
INF141 Migration of VSS and SVN to GiT |
Project Closed 12-July-2019 |
INF138 Annual DR Review |
Project Closed 2-Aug-2019 |
INF134 Logging Data Retention |
Project Closed 2-Aug-2019 |
INF133 Addressing Data Security |
Project Closed 2-Aug-2019 |
Attachment | Size |
---|---|
![]() | 297.13 KB |
![]() | 352.04 KB |