Report for May 2019
- Report Date
- May 2019
IS Applications Infrastructure Programme Report for Programme Owner Stefan Kaempf
Section One: Programme Commentary, RAG and Resources Update
Overall Programme RAG: RED
All projects planned, start dates set, continuing projects as planned or allocated budget for unplanned. Requests for project managers made and PM's have been assigned to all projects. Additional projects INF144 and INF145 added to programme.
However, an increasing number of projects are reporting lack of resource and conflict of resource - if there are no resolution in May 2019 then programme will have to re-consider viability of delivering many of its benefits in 18/19 (Risk raised)
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
Section Three: Projects in Progress
Project Info |
Project Manager's Commentary |
||||||||||||||||||||||||||||||||||||||||||
Logging Data Retention Milestones
RAG Status Green |
Report by Ian Mitchell for May 2019Achievements in last period
*1. Outstanding action - Stefan – to discuss privacy statements as regards data logging with the DPO, Service Management and the Director of Student Systems (Renate Gertz, Alex Carter and Lisa Dawson). *2. Outstanding action - Stefan – to go to the OGG and request that the ITI draft policy becomes APPs policy. Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||||||||
CF10 Updates
Milestones
There is no confidence in these dates due to latest resource issues
RAG Status AMBER |
Report by Sue Woodger for May 2019Achievements in last period
Issues
Next Steps
Commentary: Resourcing still an issue. Description: Despite having priority promoted to highest the project is again having conflict with other highest priority projects and losing those conflicts( latest has been against FIN119 again and MLE005). Impact: We are trying to move apps between environments manually but this is adding to our time to complete plus the time spent in conflicts is adding to the budget. We need Software Dev time for the Windows build but can’t get it without another conflict. Meantime the support for CF10 ran out on 16 May 2019. Plan to resolve issue/manage risk: Escalated to programme manager and project sponsor to advise how we move forward. |
||||||||||||||||||||||||||||||||||||||||||
Annual Infrastructure Rationalisation Decommissioning Milestones
RAG Status GREEN |
Report by David Watters for May 2019Achievements
Issues
Next steps
|
||||||||||||||||||||||||||||||||||||||||||
Annual DR Review and Tests Milestones
RAG Status GREEN |
Report by Ian Mitchell for May 2019Achievements in last period
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||||||||
INF139 Annual Upgrades of Development Tools + frameworks 18/19 (18-19 Project) AP89-018 Milestones
RAG Status GREEN |
Report by Anne Mathison for May 2019AchievementsPython
Bamboo
Issues
Next Steps
Python
ASTA
Bamboo
Oracle Grid
Sentry
PMP
GREEN RAG status |
||||||||||||||||||||||||||||||||||||||||||
INF140 - Middleware Patching Process Milestones TBC M3: Patch Strategies Complete TBC M4: Initial Patch Cycle Complete TBC M5: Delivery 31 July-2019 M6: Project Close
RAG Status AMBER |
Report by Karen Stirling for May 2019Achievements in Last Period
Issues
Next Steps
The project is reporting AMBER due to Description of issue/risk : Milestones require to be agreed for patching cycle activity which is expected to complete this financial year Impact on project : Budget will be reviewed and unspent days will be returned to ISG Programme Plan to resolve issue/manage risk : Meeting arranged for week commencing 10th June to map out activity and agreed new dates for remainder of project. .
|
||||||||||||||||||||||||||||||||||||||||||
Milestones
RAG Status AMBER
|
Report by Maurice Franceschi (for Nigel Binns) for May 2019
Achievements this period
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||||||||
Move IS based Oracle databases to VMs and stretched cluster Milestones
RAG Status: GREEN
|
Report by David Watters for May 2019Achievements
Issues
Next steps
|
||||||||||||||||||||||||||||||||||||||||||
INF143 - MySQL Environment Migration Milestones
RAG Status AMBER |
Report by Geoff Cropley for May 2019
Achievements in Last Period
Issues
Next Steps
The project is reporting AMBER due to; Description of issue/risk : The project is moving to deliver and close in 2019-20 however there is no budget agreed as yet for the new academic year. Impact on project: The impact of this will delay the migration of a number of services and prevent the decommissioning of the existing environments. Plan to resolve issue/manage risk: A planning request for 100 days has been lodged to support the activities to complete the migration during 2019-20. |
||||||||||||||||||||||||||||||||||||||||||
Protecting Data in the EDW Milestones
RAG Status RED |
Report by Kevin Hone for May 2019
Achievements
Issues
Next Steps
The project is reporting RED due to; Description of issue/risk : Lack of technical resource involvement/availability since scheduled project start date (due to illness). Impact on project: The timescale for delivery is likely to be a challenge. Plan to resolve issue/manage risk: To address the timescale concern, a request is to be made for additional resource to be assigned to the project. |
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
LAMP / WIMP Platform Upgrade Project Closed 12-Oct-18 |
Project Closed 12-Oct-18 |
(INF136) Annual Business Technology End of Life Analysis | Withdrawn Feb 2019 |
INF144 Encryption at Rest - Analysis |
Project Closed 3-May-2019 |
INF121 - Migrate core databases to Oracle 12c |
Project Closed 3-May-2019 |
INF129 - Wiki Database Resilience Improvement |
Project Closed 3-May-2019 |
Attachment | Size |
---|---|
![]() | 355.39 KB |
![]() | 286.2 KB |