Report for April 2019
- Report Date
- April 2019
IS Applications Infrastructure Programme Report for Programme Owner Stefan Kaempf
Section One: Programme Commentary, RAG and Resources Update
Overall Programme RAG: RED
All projects planned, start dates set, continuing projects as planned or allocated budget for unplanned. Requests for project managers made and PM's have been assigned to all projects. Additional projects INF144 and INF145 added to programme.
However, an increasing number of projects are reporting lack of resource and conflict of resource - if there are no resolution in May 2019 then programme will have to re-consider viability of delivering many of its benefits in 18/19 (Risk raised)
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
Section Three: Projects in Progress
Project Info |
Project Manager's Commentary |
||||||||||||||||||||||||||||||||||||||||||||||||
Logging Data Retention Milestones To be determined during planning
RAG Status Green |
Report by Ian Mitchell for April 2019Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||||||||||||||
CF10 Updates
Milestones
There is no confidence in these dates due to latest resource issues
RAG Status RED |
Report by Sue Woodger for April 2019Achievements in last period
Issues
Next Steps
Commentary: RAG upgraded to RED again due to resourcing issues getting Dev time resulting in no confidence in current milestones . Project is yet again competing for resource having already lost it to FIN119. Despite having priority promoted to highest the project is up against 2 other projects also with highest priority. This is pushing timescales out again and although CF10 is out of support on 16 May 2019 it is now unlikely to deliver before the end of July 2019 . The resource conflict is being submitted by FIN119 this week. It should also be noted that these resource conflicts are delaying the project considerably and we are being pushed nearer the new financial year to deliver - with no guarantee that budget will be available in 19/20 to complete this project. |
||||||||||||||||||||||||||||||||||||||||||||||||
Annual Infrastructure Rationalisation Decommissioning Milestones
RAG Status GREEN |
Report by David Watters for April 2019Achievements
Issues
Next steps
|
||||||||||||||||||||||||||||||||||||||||||||||||
Annual DR Review and Tests Milestones To be determined during planning
RAG Status GREEN |
Report by Ian Mitchell for April 2019Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||||||||||||||
INF139 Annual Upgrades of Development Tools + frameworks 18/19 (18-19 Project) AP89-018 Milestones
RAG Status GREEN |
Report by Anne Mathison for April 2019Achievements
Issues
Next Steps
GREEN RAG status |
||||||||||||||||||||||||||||||||||||||||||||||||
INF140 - Middleware Patching Process Milestones 05-April-2019 M3: Patch Strategies Complete 24-April-2019 M4: Initial Patch Cycle Complete 07-June-2019M5: Delivery 28-June-2019 M6: Project Close
RAG Status RED |
Report by Maurice Franceschi (for Karen Stirling) for April 2019Achievements in Last Period
Issues
Next Steps
The project is reporting RED as milestones have not been met and due to shortening timescales we may have to withdraw the project as delivery within 18/19 will be unrealistic and there is no budget for 19/20.
|
||||||||||||||||||||||||||||||||||||||||||||||||
Milestones
RAG Status RED
|
Report by Maurice Franceschi (for Nigel Binns) for April 2019
Achievements this period
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||||||||||||||
Move IS based Oracle databases to VMs and stretched cluster Milestones
RAG Status: GREEN
|
Report by David Watters for April 2019Achievements
Issues
Next steps
|
||||||||||||||||||||||||||||||||||||||||||||||||
INF143 - MySQL Environment Migration Milestones
RAG Status Red |
Report by Geoff Cropley for April 2019
Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||||||||||||||
Protecting Data in the EDW Milestones
RAG Status RED |
Report by Kevin Hone for April 2019
Achievements
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
LAMP / WIMP Platform Upgrade Project Closed 12-Oct-18 |
Project Closed 12-Oct-18 |
(INF136) Annual Business Technology End of Life Analysis | Withdrawn Feb 2019 |
INF144 Encryption at Rest - Analysis |
Project Closed 3-May-2019 |
INF121 - Migrate core databases to Oracle 12c |
Project Closed 3-May-2019 |
INF129 - Wiki Database Resilience Improvement |
Project Closed 3-May-2019 |
Attachment | Size |
---|---|
![]() | 293.93 KB |
![]() | 321.43 KB |