Report for April 2019

Report Date
April 2019

IS Applications Infrastructure Programme Report for Programme Owner Stefan Kaempf

 

Section One: Programme Commentary, RAG and Resources Update

Overall Programme RAG: RED

All projects planned, start dates set, continuing projects as planned or allocated budget for unplanned. Requests for project managers made and PM's have been assigned to all projects. Additional projects INF144 and INF145 added to programme.

However, an increasing number of projects are reporting lack of resource and conflict of resource - if there are no resolution in May 2019 then programme will have to re-consider viability of delivering many of its benefits in 18/19 (Risk raised)

 

 

 

 

Section Two: Projects Not Started  

Project Info Programme Manager's Commentary
   
   

Section Three: Projects in Progress

 

Project Info

Project Manager's Commentary

INF134 AP89-023

Logging Data Retention

Milestones              

 To be determined during planning

End of Planning 29-Apr-2019
Delivery 28-Jun-2019
Project Closure 12-Jul-2019

                                                                            

RAG Status

Green

Report by Ian Mitchell for April 2019

Achievements in Last Period

  • End of Planning milestone achieved 29 April. All relevant parties have now agreed on project Brief. Mark Lang; Bill Lee, Heather Larnach; Stefan Kaempf; Maurice Franceschi.

Issues

  • No major issues. 

Next Steps

  • Next steps are discuss policy. Meeting scheduled 16 May to discuss ITI draft policy and retention proposals raised by project team. PM encouraged attendees to consider potential ideas prior to next meeting.

 

INF135

CF10 Updates

 

Milestones

Build -DEV

17-May-2019  

Migration - TEST

24-May-2019

Acceptance

24-Jun-2019  

Delivery

12-Jul-2019

Close

09-Aug-2019

There is no confidence in these dates due to latest resource issues

 

RAG Status RED

Report by Sue Woodger for April 2019

Achievements in last period

  • Following the resource conflict with FIN119 we had the project priority raised to Highest wef 22 April as CF10 was out of support from 16 May 2019 meaning that the system would be unsupported with no patching done

Issues

  • We were conflicted with FIN119 at the beginning of April for Dev resource and lost as FIN119 was highest priority
  • PM understood that we were to get Dev resource back from 6 May but there are now further conflicts on Dev time. FIN119 is still ongoing and MLE005 need Dev CF time – all three projects are highest priority. Plus the same resource is also needed for timetabling

Next Steps

  • Complete build

Commentary: RAG upgraded to RED again due to resourcing issues getting Dev time resulting in no confidence in current milestones . Project is yet again competing for resource having already lost it to FIN119. Despite having priority promoted to highest the project is up against 2 other projects also with highest priority. This is pushing timescales out again and although CF10 is out of support on 16 May 2019 it is now unlikely to deliver before the end of July 2019 . The resource conflict is being submitted by FIN119 this week. It should also be noted that these resource conflicts are delaying the project considerably and we are being pushed nearer the new financial year to deliver - with no guarantee that budget will be available in 19/20 to complete this project.

 

INF137

Annual Infrastructure Rationalisation Decommissioning

Milestones

Stage Milestone Due Date
Deliver Delivery complete (DSOR) 31-May-2019
Close Project Closure 14-Jun-2019

RAG Status

 GREEN

Report by David Watters for April 2019

Achievements

  • More work on updating server listings
  • Communications with Windows 2012 servers/business owners
  • Checking of RedHat/CentOS 6 servers
  • Planning of any decommissions that are 'orphaned'

Issues

  • Remaining milestones adjusted to accommodate final updates and additional decommissions

Next steps

  • Finalise extra decommissions and update listings
  • Closure of project

INF138 AP89-017

Annual DR Review and Tests

Milestones              

 To be determined during planning

End of Planning 29-Mar-2019
Delivery 14 Jun-2019
Project Closure 28-Jun-2019

                                                            

RAG Status

GREEN

Report by Ian Mitchell for April 2019

Achievements in Last Period

  • End of Planning milestone achieved 10 April.  Lawrence Stevenson added as stakeholder for information as regards ITI related testing project..

Issues

  • No major issues.  

Next Steps

  • Review current DR documentation.
  • Meeting scheduled on 14 May. DevTech’s Ewan Scott currently reviewing DR documentation for High and Medium Priority Services, before passing to TechMan team

INF139 Annual Upgrades of Development Tools + frameworks 18/19 (18-19 Project)

AP89-018

Milestones

Stage Milestone Date
Accept Python Build / Acceptance Signoff 10-May-2019
Deliver Python Deployed Signoff 22-May-2019
Accept Oracle Grid Acceptance Signoff 06-Jun-2019
Accept Sentry Build / Acceptance Signoff 07-Jun-2019
Accept Bamboo Build / Acceptance Signoff 12-Jun-2019
Deliver Sentry Deployed Signoff 12-Jun-2019
Design ASTA Requirements Design Signoff 17-June-2019
Deliver Oracle Grid Deployed Signoff 20-Jun-2019
Deliver Bamboo Deployed Signoff 24-Jun-2019
Accept Over All Build / Acceptance Sign Off 28-Jun-2019
Accept PMP Build / Acceptance Signoff 28-Jun-2019
Deliver ASTA Requirements Document Signoff 28-June-2019
Deliver PMP Deployed Signoff 12-Jul-2019
Deliver Overall Deployment Sign-Off 12-Jul-2019
Close Close 02-Aug-2019

 

RAG Status

 GREEN

Report by Anne Mathison for April 2019

Achievements

  • Python Software Developer been reassigned as previous one was taken up by another project
  • Revised Python milestones have been agreed and planned
  • No other progress this month

 

  • ASTA discussions have been held with directorate
  • Supplier meeting to be planned in June

 

  • Nexus progress was kept separate from Bamboo
  • Nexus Build Acceptance Signoff successfully completed mid April
  • Nexus Deployed Signoff deployed successfully on 25-April

 

  • Bamboo now delayed until June
  • Deprecated code to be identified, could affect up to 40 plans

 

  • Sentry has been re-planned around summer holidays
  • Sentry re-planned for June

Issues

  • No issues

Next Steps

  • Python QA to complete - Puppet Code will go in first (Dev Tech) and Bamboo plan follows after that (Software Dev)
  • Hand over Python work to Apps Support

  • Completion of documentation updates
  • Sign off Python Acceptance Testing in May
  • Deploy Python in May

 

  • ASTA versions to be discussed with the supplier in June
  • ASTA requirements will be completed in June
  • ASTA JIRAs to be set up for the tasks required in June

 

  • Bamboo project milestones have been amended to June
  • Agree and schedule Bamboo Go Live
  • Set up Service Alert for Bamboo
  • Set up Go Cab for Bamboo
  • Bamboo deployed to LIVE

 

  • Start on Oracle Grid work

GREEN RAG status

INF140 - Middleware Patching Process

Milestones

05-April-2019  M3: Patch Strategies Complete

24-April-2019 M4: Initial Patch Cycle Complete

07-June-2019M5: Delivery

28-June-2019 M6: Project Close

 

RAG Status

RED

Report by Maurice Franceschi (for Karen Stirling) for April 2019

 

Achievements in Last Period

  • No patching strategies completed this month
  • Additional components have been raised to include within register, to be reviewed with the project team for inclusion

Issues

  • Completion of patching strategies has stopped with little or no activity completed
  • Resource assigned to project have been involved or aligned to other priority work and have had no time to work on this project
  • It was agreed to hold a workshop session so that the whole team could work on the strategies together away from distractions, this session was arranged for 2nd May however limited acceptance to session which resulted in session being cancelled. PM is arranging further timeslots to complete from we/c 13th May if this fails to result in any progress, the only option will be to suggest that if these meetings are not held soon then we look to withdraw the project as delivery within 18/19 will be unrealistic and there is no budget for 19/20.
  • Milestones to be reviewed

Next Steps

  • Arrange session for week commencing 13th May to complete strategies

 

The project is reporting RED as milestones have not been met and due to shortening timescales we may have to withdraw the project as delivery within 18/19 will be unrealistic and there is no budget for 19/20. 

 

 

 

 

 

INF141 (18-19 Project)

Milestones

Analyse Complete Data on VSS Projects 12-Dec-2018
Analyse Complete Data on SVN Projects 12-Dec-2018
Analyse Migration Decision 14-Dec-2018
Deliver Complete Migrations 28-Jun 2019
Close Closure

12

Jul-2019

 

 

 

RAG Status

RED

 

 

 

Report by Maurice Franceschi (for Nigel Binns) for April 2019

 

Achievements this period

  • review approach, plan and process with Bill Lee and team - done
  • resourcing  - not fully assigned

Issues

  • software development resources booked - still not fully resourced

Next Steps

  • resource clarification and assignments
  •  

INF142 (18-19 Project)

Move IS based Oracle databases to VMs and stretched cluster

Milestones

Stage Milestone Due Date
Plan Planning Stage Complete 17-May-2019
Deliver Delivery complete 05-Jun-2020
Close Project Closure 26-Jun-2020

 

 

RAG Status: GREEN

 

Report by David Watters for April 2019

Achievements

  • Work on project brief - particularly around scope and deliverables
  • Discussions round RedHat/CentOS licensing issues and server numbers

Issues

  • Planning milestone extended due to PM workload

Next steps

  • Finalisation of project brief, including estimate, plan and updated risk and stakeholder logs
  • Work to start on analysis of server estate and licences required

INF143 - MySQL Environment Migration

Milestones

Plan End of Planning 14-Nov-2018
Analyse         Application Register Complete 11-Jan-2019
Design Infrastructure Design Complete        01-Feb-2019
Build Acceptance Sign-off 09-May-2019
Build Infrastructure Build Complete 14-May-2019
Deliver Delivery sign-off 24-Jul-2019
Close Project Close 02-Aug-2019

 

RAG Status

Red

Report by Geoff  Cropley for April 2019

 

Achievements in Last Period

  • Puppet build automation has been completed.  There are outstanding Firewall rules to be created and a number of exceptions to be added
  • Server mirroring has to be set-up.  This is currently being done manually

Issues

  • None

Next Steps

  • Request Test environment servers for all instances
  • Commence migration to Dev and Test servers
  • Commence Testing

 

 

INF145 (18-19 Project)

Protecting Data in the EDW

Milestones

 Plan  Draft Project Brief       10/05/19     
 Plan  End of Planning        17/05/19
 Build  TBC    TBC
 Deliver  TBC    17/07/19
 Close  Project Close    31/07/19

 

 

RAG Status

RED

Report by Kevin Hone for April 2019

 

Achievements

  • The project initiation paper was approved at WIS on the 26th April subject to revisions which were completed on the 29th April.

Issues

  • The project has only latterly started and without a proper understanding of scope, timelines could prove to be a challenge to complete all work by end of the reporting year (i.e. end of July).
  • Project resource has yet to be identified and secured.

Next Steps

  • A technical workshop is to be arranged to confirm project cope, understanding and shape the content of the Project Brief.
  • Project planning to be progressed.

 

Section Four: Closed or Withdrawn Projects

 

 

Project Info Project Managers Commentary

INF127 (17-18 Project)

LAMP / WIMP Platform Upgrade

Project Closed 12-Oct-18

Closure Report

Closure Milestone

Project Closed 12-Oct-18

(INF136) Annual Business Technology End of Life Analysis Withdrawn Feb 2019
INF144 Encryption at Rest - Analysis

Closure Report

Project Closed 3-May-2019

INF121 - Migrate core databases to Oracle 12c

Closure Report

Project Closed 3-May-2019

INF129 - Wiki Database Resilience Improvement

Closure Report

Project Closed 3-May-2019