Report for February 2019

Report Date
February 2019

IS Applications Infrastructure Programme Report for Programme Owner Stefan Kaempf

 

 

 

Section One: Programme Commentary, RAG and Resources Update

Overall Programme RAG: GREEN

All projects planned, start dates set, continuing projects as planned or allocated budget for unplanned. Requests for project managers made and PM's have been assigned to all projects. Additional project INF144 added to programme.

 

 

 

Section Two: Projects Not Started  

Project Info Programme Manager's Commentary
   
(INF142) Move IS based Oracle databases to VMs and stretched cluster Start Date  8/3
   

Section Three: Projects in Progress

 

Project Info

Project Manager's Commentary

INF121 (17-18 project)

Migrate Core Databases to Oracle 12c

Milestones

Stage Milestone Due Date
Deliver AppsLive deployment sign off 04-Apr-2019
Close Closure 11-Apr-2019

RAG Status

GREEN

 

Report by David Watters for February 2019

Achievements this Period

  • Work on 'mopping up' tasks continued

Issues

  • Closure date revised

Next Period

  • Project closure

 

 

INF129 (17-18 Project)

Database Resilience 17-18

Milestones              

  

Stage Milestone Due Date
Deliver Phase 2 - Stage 1 Database move to VM - Delivery Complete 15-Mar-2019
Close Project Close complete 29-Mar-2019

                                                                             

RAG Status

 AMBER - replan of milestones finalised.

 

 

 

Report by David Watters for February 2019

Achievements This Period

  • Meetings between project team to discuss direction

  • Project milestones reviewed and replanned

Issues

  • Outstanding milestones to be revised
  • Extra effort required to complete project

Next Steps

  • Complete Puppet work

  • Finalise migration of Dev Wki

  • Close project

 

 

 

 

 

   

INF134 AP89-023

Logging Data Retention

Milestones              

 To be determined during planning

End of Planning 08-Mar-2019
Delivery 31-May-2019
Project Closure 14-Jun-2019

                                                                            

RAG Status

GREEN

Report by Colin Watt for February 2019

Achievements in Last Period

  • Project Sponsor and Team kickoff meeting w/c 11/02/19.
  • Project brief and estimates in draft.

Issues

  • No major issues. Time constraints on project team for completing planning, but no concerns once planning agreed.

Next Steps

  • Complete project brief and estimates.
  • Agree scope and sign off planning milestone with TechMan, DevTech, ITI on planning and estimates.

 

INF135

CF10 Updates

 

Milestones

Build

Build

29-Mar-2019

Build

Migration

19-Apr-2019

Accept

Acceptance

17-May-2019

Deliver

Delivery

27-May-2019

Close

Close

21-Jun-2019

 

RAG Status GREEN

Report by Sue Woodger for February 2019

 

Achievements in last period

  • Reviewed costs and plan for development work with programme manager 20 Feb 19
  • DevTech completed Dev build on KB server and modified Bamboo on Dev for Cesar and AIR. Cesar will be the proof of concept application
  • DevTech have spent a lot of time (10d) getting Puppet ready – but this has included the building of the Dev server, updated the settings and updated the documentation. This work now has to be signed off by Dev team before DevTech can continue with the build
  •  DevTech found an issue with one of the frameworks (Coldspring) and put a manual fix on the server and needs someone in Dev to put into version control and create a Bamboo plan. He also needs advice from Dev Team on what branch should be used etc

Issues

  • Submitted request for development resource on 6 February and this was answered by resourcing manager on 7/2 that the developer has no time until April. PM then asked who else could do this work but received no reply. PM tried to follow up but resourcing manager was on leave. PM emailed for his return on 18/2 stating that he hadn’t informed who could do this work – PM pointed out that the booking was still in asta and if he couldn’t assign it all can he assign the urgent work (as detailed to him i.e. the work identified in achievements section above) . PM followed this up on 20//192 as still no reply. PM was then copied into an email to developer assigning his time from 1 March to 18 April. There was no acknowledgement of the urgent work to be done to allow continuation of build. This means that work on build cannot continue until after developer has completed those urgent tasks wef 1/3/19. This has delayed build work and revised milestones had to be submitted to WIS 20/2/19.

Next Steps

  • Developer to start in urgent tasks wef 1 Mar
  • This will then allow DevTech to continue with build work

 

 

INF137

Annual Infrastructure Rationalisation Decommissioning

Milestones

Stage Milestone Due Date
Deliver Delivery complete (DSOR) 29-Mar-2019
Close Project Closure 12-Apr-2019

RAG Status

 GREEN

Report by David Watters for February 2019

Achievements

  • Identification of Windows 2012 servers/business owners
  • Cross-checking with ENT023 project finalised
  • More work on Windows 2008 outstanding items

Issues

  • None

Next steps

  • Final work on server listings
  • Communications with Windows 2012 servers/business owners
  • Checking of RedHat 6 servers
  • Planning of any decommissions that are 'orphaned'

INF138 AP89-017

Annual DR Review and Tests

Milestones              

 To be determined during planning

End of Planning 08-Mar-2019
Delivery 31-May-2019
Project Closure 14-Jun-2019

                                                            

RAG Status

GREEN

Report by Colin Watt for February 2019

Achievements in Last Period

  • Project Sponsor and Team kickoff meeting w/c 11/02/19.
  • Project brief and estimates in draft.
  • PM discussion with PM of ENT038 - PM added to INF138 as stakeholder

Issues

  • No major issues. Time constraints on project team for completing planning, but no concerns once planning agreed.

Next Steps

  • Complete project brief and estimates.
  • Agree scope and sign off planning milestone with TechMan, DevTech, ITI on planning and estimates.

INF139 Annual Upgrades of Development Tools + frameworks 18/19 (18-19 Project)

AP89-018

Milestones

Stage Milestone Due Date
Accept Python Build / Acceptance Signoff 06-Mar-2019
Accept Nexus Build / Acceptance Signoff 07-Mar-2019
Deliver Python Deployed Signoff 12-Mar-2019
Deliver Nexus Deployed Signoff 14-Mar-2019
Design ASTA Requirements Design Signoff 18-Mar-2019
Deliver ASTA Requirements Document Signoff 28-Mar-2019
Accept Bamboo Build / Acceptance Signoff 01-Apr-2019
Deliver Bamboo Deployed Signoff 12-Apr-2019
Accept Oracle Grid Acceptance Signoff 19-Apr-2019
Deliver Oracle Grid Deployed Signoff 03-May-2019
Accept Over All Build / Acceptance Sign Off 28-Jun-2019
Accept PMP Build / Acceptance Signoff 28-Jun-2019
Accept Sentry Build / Acceptance Signoff 28-Jun-2019
Deliver PMP Deployed Signoff 12-Jul-2019
Deliver Sentry Deployed Signoff 12-Jul-2019
Deliver Overall Deployment Sign-Off 19-Jul-2019
Close Close 02-Aug-2019

RAG Status

 GREEN

Report by Anne Mathison for February 2019

 

Achievements

  • Python - Due to key project team absences the UAT signoff and Delivery dates have had to be delayed until March
    • Python - new milestone dates have been agreed with the Programme Manager
  • Python Alert for Go Live amended to March

  • Request for Change re Go Live for Python deployment in March amended

 

  • Due to key PMO ASTA project team absences the ASTA milestones have had to be delayed until March
    • ASTA requirements completion  delayed until March to allow more time
    • ASTA - milestone dates have been amended and agreed with the ASTA programme
    • This may still be further delayed as initial talks with supplier have not been arranged as yet

 

  • Nexus has been deployed to Test

Issues

  • No issues

Next Steps

  • Resolve a misconfiguration issue between Python version as configured on infrastructure vs Python version as configured on build / deployment.

    • Once above resolved, update Python documentation re Bamboo plan configuration.
  • Python QA to complete - Puppet Code will go in first (Dev Tech) and Bamboo plan follows after that (Software Dev)
  • Hand over Python work to Apps Support

  • Completion of documentation updates
  • Sign off Python Acceptance Testing in March
  • Deploy Python during March

 

  • ASTA versions to be discussed with the supplier
  • ASTA requirements will be completed in March
  • ASTA JIRAs to be set up for the tasks required

 

  • Review Nexus and update test coverage in Test
  • Apply  upgrade to Test
  • Test processes in Test
  • Acceptance Signoff in Test
  • Review schedule, possibilities and downtime impact
  • Agree and schedule Nexus Go Live
  • Set up Service Alert for Nexus
  • Set up Go Cab for Nexus
  • Nexus deployed to LIVE

 

  • Bamboo upgrade work will start in March
  • Bamboo Acceptance Testing will be virtually complete

 

GREEN RAG status

INF140 - Middleware Patching Process

Milestones

05-April-2019  M3: Patch Strategies Complete

24-April-2019 M4: Initial Patch Cycle Complete

07-June-2019M5: Delivery

28-June-2019 M6: Project Close

 

RAG Status

GREEN

Report by Karen Stirling for February 2019

Achievements in Last Period

  • Template created for patching process documentation
  • Development Team and Tech Man Resources identified
  • Patch Strategy document created for Java and Coldfusion

Issues

  • Project team have reviewed initial planning milestones and agreed to move project closure out to end of June as there are no key dependencies on project completing by April
  • Revised milestones to be submitted to WIS for approval and approved given by Project Sponsor

Next Steps

  • Aim to complete priority components in next month and those which are easiest to tackle

 

The project is reporting GREEN

 

 

 

INF141 (18-19 Project)

Milestones

Analyse Complete Data on VSS Projects 12-Dec-2018
Analyse Complete Data on SVN Projects 12-Dec-2018
Analyse Migration Decision 14-Dec-2018
Deliver Complete Migrations 28-Jun 2019
Close Closure

12

Jul-2019

 

 

 

RAG Status

Red

 

 

 

Report by Maurice Franceschi for February 2019

 

Achievements this period

  • resource partially assigned - up to April
  • PM was not changed

Issues

  • software development resources booked - still not fully resourced

Next Steps

  • resourcing up to end of June 
  • continue with priority list of Apps

INF143 - MySQL Environment Migration

Milestones

02-Nov-2018      End of Planning 05-Jun-2019        Deployment Sign-off 26-Jun-2019        Project Close

Milestones

Plan End of Planning 14-Nov-2018
Analyse         Application Register Complete 11-Jan-2019
Design Infrastructure Design Complete        01-Feb-2019
Build Acceptance Sign-off 09-May-2019
Build Infrastructure Build Complete 14-May-2019
Deliver Delivery sign-off 21-May-2019
Close Project Close 18-Jun-2019

 

RAG Status

Green

Report by Geoff  Cropley for February 2019

 

Achievements This Period

  • Confirmation from OGG the use and migration from MySQL to Maria DB
  • Puppet build automation in progress 
  • Plan and estimate under review with the potential to complete as many applications as possible within the academic year and budget

Issues

  • None

Next Steps

  • Agree revised application inventory
  • Build Development environment using Puppet automation

 

 

 

INF144 (18-19 Project)

Milestones

 Plan  Scope document 16-Nov-2018
 Deliver    Initial Draft Recommendation Report 17-Dec-2018
 Plan  End of Planning     21-Dec-2018
 Deliver  Final Recommendation Report 25-Jan-2019
 Deliver  Approved plan and approach to deliver encryption at rest.   15-March-2019
 Close  Project Close 29-March-2019

 

 

RAG Status

Green

 

 

 

Report by Ken Miller for February 2019

 

Achievements

  • Phase 2 scoping exercise to discuss approach and timescales rearranged due to last minute resource conflict.

Issues

Next Steps

  • Phase 2 scoping exercise held to discuss approach and timescales.
  • Report detailing phase 2 approach and plan forwarded to stakeholders.
  • Close project.

 

 

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

INF127 (17-18 Project)

LAMP / WIMP Platform Upgrade

Project Closed 12-Oct-18

Closure Report

Closure Milestone

(INF136) Annual Business Technology End of Life Analysis Withdrawn Feb 2019