Report for January 2019
- Report Date
- January 2019
IS Applications Infrastructure Programme Report for Programme Owner Stefan Kaempf
Section One: Programme Commentary, RAG and Resources Update
Overall Programme RAG: GREEN
All projects planned, start dates set, continuing projects as planned or allocated budget for unplanned. Requests for project managers made and PM's have been assigned to all projects. Additional project INF144 added to programme.
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
(INF136) Annual Business Technology End of Life Analysis | Start Date 8/2 |
(INF142) Move IS based Oracle databases to VMs and stretched cluster | Start Date 8/2 |
Section Three: Projects in Progress
Project Info |
Project Manager's Commentary |
||||||||||||||||||||||||||||||||||||
Migrate Core Databases to Oracle 12c Milestones
RAG Status GREEN
|
Report by David Watters for January 2019Achievements this Period
Issues
Next Period
|
||||||||||||||||||||||||||||||||||||
Database Resilience 17-18 Milestones
RAG Status AMBER - replan of milestones to be finalised.
|
Report by David Watters for January 2019
Achievements This Period
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||
Logging Data Retention Milestones To be determined during planning
RAG Status GREEN |
Report by Colin Watt for January 2019Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||
CF10 Updates
Milestones
RAG Status GREEN |
Report by Sue Woodger for January 2019January 19 Achievements in last period
Issues
Next Steps
RAG Commentary: N/A Project is GREEN
|
||||||||||||||||||||||||||||||||||||
Annual Infrastructure Rationalisation Decommissioning Milestones
RAG Status GREEN |
Report by David Watters for January 2019Achievements
Issues
Next steps
|
||||||||||||||||||||||||||||||||||||
Annual DR Review and Tests Milestones To be determined during planning
RAG Status GREEN |
Report by Colin Watt for January 2019Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||
INF139 Annual Upgrades of Development Tools + frameworks 18/19 (18-19 Project) AP89-018 Milestones
RAG Status GREEN |
Report by Anne Mathison for January 2019
Achievements
Issues
Next Steps
GREEN RAG status |
||||||||||||||||||||||||||||||||||||
INF140 - Middleware Patching Process Milestones 12-Feb-2019 M3: Patch Strategies Complete 01-Mar-2019 M4: Initial Patch Cycle Complete 19-Apr-2019 M5: Delivery 03-May-2019 M6: Project Close
RAG Status Green |
Report by Karen Stirling for January 2019Achievements in Last Period
IssuesMilestone for completing strategies may need to be revised due to availability of Dev Tech resource Next Steps
The project is reporting GREEN.
|
||||||||||||||||||||||||||||||||||||
Milestones
RAG Status Red
|
Report by Maurice Franceschi for January 2019
Achievements this period
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||
INF143 - MySQL Environment Migration Milestones 02-Nov-2018 End of Planning 05-Jun-2019 Deployment Sign-off 26-Jun-2019 Project Close Milestones
RAG Status Green |
Report by Geoff Cropley for January 2019
Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||
Milestones
RAG Status Green
|
Report by Ken Miller for January 2019
Achievements
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
LAMP / WIMP Platform Upgrade Project Closed 12-Oct-18 |
|