July 2015
- Report Date
- July 2015
IS Applications Infrastructure Programme Report for Programme Owner Stefan Keampf
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Overall Programme RAG: GREEN
The programme closes 14/15 in a strong position.
All projects planned to deliver and complete this year have, apart from INF108 which has just a little effort carried over onto 2015/16, closing in August.
Little of the programme contingency was needed.
There was enough budget to start off three 15/16 projects in July, enhancing the chances of another successful programme delivery next year.


Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
System Monitoring Solution - Implementation
| INF107 having completed, the next project will split into a Pilot phase to validate the technical solution and the process changes recommended, before procurement/implementation. We had hoped to start this in 2014/15 but due to other priorities and resource constraints, will start in Q3/Q4 2015 once we have discussed with colleagues in ITI.
|
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||||||||||||
| INF105 (AP45-053) Decommission Obsolete Infrastructure Category: Core Funding
Milestones
RAG Status GREEN | Report by David Watters for July 2015Achievements this Period
Issues
Next Steps
| ||||||||||||||||||
Automated Server Builds Category: Discretionary
Milestones
RAG Status AMBER
| Report by Colin Watt for July 2015
Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||||
Install Oracle 12c Category: Compliance
Milestones
RAG Status GREEN | Report by David Watters for July 2015
Achievements in Last Period
Issues
Next Period
| ||||||||||||||||||
New SQL Server Database Tier Replacement Category: Compliance
Milestones
RAG Status GREEN | Report by Karen Stirling for July 2015
Achievement in Last Period
Issues None
Next Steps
The project status is GREEN | ||||||||||||||||||
Build and Configure new ColdFusion Version [15/16] Category: Compliance
Milestones
RAG Status GREEN | Report by Gillian Henderson for July 2015
Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
New Application Tier Replacement Category: Compliance | Project closed on 6th February 2015. Closure Report |
Annual upgrades of development tools (JIRA/Bamboo) Category: Compliance | Project closed on 25th June 2015. Closure Report |
Environment Monitoring System Category: Discretionary | Project closed on 3rd July 2015. Closure Report |