April 2015
- Report Date
- April 2015
Infrastructure Programme Report for Programme Owner David Smyth
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Overall Programme RAG: GREEN
The current projects remain on course for completion in the year.
As all the current projects are now in ASTA and resourced, Programme Status is Green.
The INF107 project is taking longer to report than had been estimated, so it may be there is insufficient time to burn through the 50 days that had been planned for the follow on project. A contingency of 27 days remains available to the programme, and the recommendation is to keep these in case of need of more budget in INF105 or INF108 and perhaps to allow some 15/16 project to start early.
There are a number of actions from the INF104 for the programme to progress. These are listed in a dedicated page. https://www.projects.ed.ac.uk/programmepage/30193. The next programme meeting will review and decide if these actions are still required.


Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
System Monitoring Solution - Implementation
| Depending on the outcome of the INF107 project, this may be a procurement or an in-house build. The project effort for this year is 50 days, but this is a multi-year project over three years. This project will start in June, if the recommendations are accepted by management. |
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||||||||||||
| INF105 (AP45-053)
Decommission Obsolete Infrastructure Category: Core Funding
Milestones
RAG Status GREEN | Report by David Watters for April 2015Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||||
|
Environment Monitoring System Category: Core Funding
Milestones
RAG Status GREEN | Report by Maurice Franceschi for April 2015
The team have started on final assessment, recommendation and report. Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||||
Automated Server Builds Category: Discretionary
Milestones
RAG Status GREEN
| Report by Colin Watt for April 2015
Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||||
Annual upgrades of development tools (JIRA/Bamboo) Category: Compliance
Milestones
RAG Status GREEN
| Report by Gillian Henderson for April 2015
Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
New Application Tier Replacement Category: Compliance | Project closed on 6th February 2015. Closure Report |
