April 2015

Report Date
April 2015

Infrastructure Programme Report for Programme Owner David Smyth

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

Overall Programme RAG: GREEN

The current projects remain on course for completion in the year.

As all the current projects are now in ASTA and resourced, Programme Status is Green.

The INF107 project is taking longer to report than had been estimated, so it may be there is insufficient time to burn through the 50 days that had been planned for the follow on project. A contingency of 27 days remains available to the programme, and the recommendation is to keep these in case of need of more budget in INF105 or INF108  and perhaps to allow some 15/16 project to start early.  

There are a number of actions from the INF104 for the programme to progress. These are listed in a dedicated page. https://www.projects.ed.ac.uk/programmepage/30193. The next programme meeting will review and decide if these actions are still required.

 

 

 

 

 

 

Section Two: Projects Not Started  

Project InfoProgramme Manager's Commentary

System Monitoring Solution - Implementation

 

Depending on the outcome of the INF107 project, this may be a procurement or an in-house build.

The project effort for this year is 50 days, but this is a multi-year project over three years.

This project will start in June, if the recommendations are accepted by management.

 

Section Three: Projects in Progress

 

Project InfoProject Managers Commentary
INF105 (AP45-053)

Decommission Obsolete Infrastructure

Category: Core Funding

 

Milestones

07-May-2015Unix decommissioning (14-15) completed
11-May-2015Password Manager work completed
13-May-2015TSM work completed
25-Jun-2015Windows decommissioning (14-15) completed
02-Nov-2015Unix decommissioning (15-16) completed
16-Nov-2015RedHat decommissioning (15-16) completed
30-Nov-2015Recommendations and procedures signed off
07-Dec-2015Windows decommissioning (15-16) completed
17-Dec-2015Closure

 

 

 

RAG Status

GREEN

Report by David Watters for April 2015

Achievements in Last Period

 

  • TSM established and deployed in LIVE environment
  • Plans for next batch of servers finalised
  • Build of replacement SOA DEV environment tested successfully  

Issues

  • Deployment of TSM in LIVE taking longer than anticipated
  • Delays to sign off of new SOA DEV environment  

Next Steps

  • Password Manager deployment to be completed
  • 'Priority 1' servers to be removed from network
  • 'Priority 2' decommissions to commence
  • Implementation of TSM to be signed off

 

INF107 (AP45-067)

Environment Monitoring System

Category: Core Funding

 

Milestones

 

29-May-2015Recommendation after Visits to Institutions
12-Jun-2015Closure

 

 

 

 

RAG Status

GREEN

Report by Maurice Franceschi for April 2015

 

The team have started on final assessment, recommendation and report.  

Achievements in Last Period

  • write report with recommentation for management - not achieved

Issues

  • no open issues or risks

Next Steps

  • write report with recommentation for management

 

 

 

INF108 (AP45-034)

Automated Server Builds

Category: Discretionary

 

Milestones

 

29-May-2015Release 4 - Moodle environment
05-Jun-2015Recommendations
26-Jun-2015Closure

 

 

 

 

 

 

RAG Status

GREEN

 

Report by Colin Watt for April 2015

 

Achievements in Last Period

  • Puppet configuration tools have been used to deploy an enhanced pilot Python development environment (Release 3 Milestone), based on Dev Services feedback.
  • PM and Senior Supplier have agreed with project Sponsor of TEL022 that the tools will be used to deploy the platform for the upgrade project.

 

Issues

  • Ensuring that the tools and processes are fit for purpose for deploying key services. PM and Senior Supplier have arranged a review meeting for w/c 04/05/15 to ensure that ITI and IS Apps are in agreement that the tools and processes are ready to proceed with delivering the platform for TEL022 Moodle Upgrade.
  • Ensuring that timelines and resource availability are adjusted to align with TEL022 milestones. A new milestone has been added for this release.

 

Next Steps

  • The next release will be to support provision of the platform for TEL022 Moodle Upgrade
  • Review of milestones, project deliverables, and project timescale.

INF109 (AP45-033)

Annual upgrades of development tools (JIRA/Bamboo)

Category: Compliance

 

Milestones

07-May-2015Build Review - JIRA/JIRA Agile
14-May-2015Delivery - Bamboo
28-May-2015Deployment Sign Off - Bamboo
28-May-2015Acceptance - JIRA/JIRA Agile
01-Jun-2015Delivery - JIRA/JIRA Agile
16-Jun-2015Deployment Sign Off - JIRA/JIRA Agile
26-Jun-2015Closure

 

 

 

 

 

RAG Status

GREEN

 

 

Report by Gillian Henderson for April 2015

 

Achievements in Last Period

  • Test upgrade of Bamboo complete
  • Testing of Bamboo upgrade complete and successful.
  • Bamboo TAD moved to new template and updated and reviewed.
  • Build/Acceptance sign off for Bamboo complete.
  • Dev upgrade of Bamboo complete.
  • Testing of dev Jira complete and successful.
  • Jira TAD moved to new template and updated and reviewed.
  • Build sign off for Jira complete.
  • Work on script change required for licensing issue with Jira carried out. It was not possible to apply similar fix that had been applied to Confluence (the same Java call not available in Jira). No further development will be carried out within this project. Bill will contact Atlassian support to see if there is another Java call that could be referenced.

Issues

  • The Bamboo Build/Acceptance and Deployment milestones were impacted by a service issue with the production Bamboo server, integration2.is. The problem with the disk has now been resolved but this impacted on Technology Managements availability and therefore the sign off of test. Build/Acceptance sign off now achieved and a new date for the live migration has been scheduled.  

Next Steps

  • Refresh of test Jira to be completed
  • Upgrade of Test Jira to be completed.
  • Testing of Jira test environment.
  • Jira Acceptance Sign off.
  • Bamboo Live upgrade to be completed.
  • Deployment sign off of Bamboo.

 

 

Section Four: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

INF106 (AP45-032)

New Application Tier Replacement

Category: Compliance

Project closed on 6th February 2015.  Closure Report