January 2015
- Report Date
- January 2015
Infrastructure Programme Report for Programme Owner David Smyth
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Overall Programme RAG: GREEN
The current projects remain on course for completion in the year, with plans and being fully resourced.
However, with the INF105 Decomisison Infrastructure project having taken almost six months to get to the end of planning, INF106 Automated Server Builds having slipped a month in planning, and INF107 Environment Monitoring Assessment stretching out to April to allow the assessment of more products, the programme manager has recommended decreasing the effort on the follow up to INF107 by 50 days and addign this effort for future years. There is still 78 days contingency available to the programme.
There are a number of actions from the INF104 for the programme to progress. These are listed in a dedicated page. https://www.projects.ed.ac.uk/programmepage/30193.
As can be seen from the RAG table, the burn rate for the first half of the year has been lower than anticipated, leaving around 360 days to be used in the next six months. However, as all the current projects are now in ASTA and resourced, Programme Status is Green.


Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
| Annual upgrades of development tools (JIRA, Bamboo, etc) | The Division has built up reliance on a number of key products over the years to assist in project and service delivery. This project would apply relevant upgrades to the following products as required: JIRA JIRA Agile Bamboo ASTA We will look to upgrade to latest stable and supported versions of the products above. This will not review new functionality and only concentrate on software upgrades.
Current feedback is that There will be no ASTA Upgrade this year The JIRA upgrades are not required until April. Bamboo Upgrade will also start in April. This project will now start in April. |
System Monitoring Solution - Implementation
| Depending on the outcome of the INF107 project, this may be a procurement or an in-house build. The project effort for this year is 50 days, but this is a multi-year project over three years. This project will start in May. |
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||||||||||||||||||||||||
| INF105 (AP45-053)
Decommission Obsolete Infrastructure Category: Core Funding
Milestones
RAG Status GREEN | Report by David Watters for January 2015Achievements this Period
Issues
Next Steps
| ||||||||||||||||||||||||||||||
New Application Tier Replacement Category: Compliance
Milestones
RAG Status GREEN | Report by Adam Wadee for January 2015
Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||||||||||||||||
|
Environment Monitoring System Category: Core Funding
Milestones
RAG Status GREEN | Report by Maurice Franceschi for January 2015
Report Date: January 2015The project milestones have been moved back further, in part due to Imperial not having availability until March, but also, the project team have decided to look at whether existing tools in use by Unix, Architecture and Edina coudl provide our solution. This reduced the amount of time left to do the follow on project to procure/build a solution, so the effort estimated has been reduced in this year and moved to 15/16 and 16/17. The staus of the project remains Green, but any further slippage would set it to Amber. Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||||||||||||||||
Automated Server Builds Category: Discretionary
Milestones
RAG Status GREEN
| Report by Colin Watt for January 2015
Achievements this period
Issues The nature of the project presents challenges to ensure tight control of resources and granular representation of tasks within Asta. PM and Senior Supplier to address this and regularly review estimates against actual effort to reduce project risk. Arranging meetings to include the wider project team and stakeholders is challenging and there have been some resource conflicts resulting in delays to meetings; the initial meetings have also been rushed due to diary commitments. PM has requested some flexibility and an acknowledgment that not everybody may be able to attend every meeting; however if this continues to be a problem, it may result in further delays to project milestones.
Next Steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
| No projects closed |
