Infrastructure Programme Report for Programme Owner David Smyth
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
With the last project planed for calendat year 2014 initiated, the project delivery and budget remains good.
There is a slight concenr over the delay in getting INF105 under way, and the resulting lower burn rate than expected, but we will review the development at the end of November by when we expect to see the project fully under way.
No concerns over INF107 or INF106.
Budget estimate is a handful of days over, but this is not a concern given the number of days relative to the programme size and contingency available.
There are a number of actions from the INF104 for the programme to progress. These are listed in a dedicated page. https://www.projects.ed.ac.uk/programmepage/30193


Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
| Annual upgrades of development tools (JIRA, Bamboo, etc) | The Division has built up reliance on a number of key products over the years to assist in project and service delivery. This project would apply relevant upgrades to the following products as required: JIRA JIRA Agile Bamboo ASTA We will look to upgrade to latest stable and supported versions of the products above. This will not review new functionality and only concentrate on software upgrades.
Current feedback is that There will be no ASTA Upgrade this year The JIRA upgrades are not required until April. Bamboo Upgrade will also start in April. This project will now start in April. |
| Automated Server Builds | This project is to take forward the recommendations of the current 13/14 project to produce a proof of concept. This project will provide the necessary production infrastructures required to deploy new environments and will produce a list of environments that can be managed under the service. The project would also produce recommendations for future projects and how to incorporate new services into the automated build system. The project wil be managed by the new project manager starting in November. This project will start on 10th November. INF108. Clon Watt as project manager.
|
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||||||||
| INF105 (AP45-053)
Decommission Obsolete Infrastructure Category: Core Funding
Milestones
RAG Status GREEN | Report by David Watters for October 2014Achievements this Period
Issues
Next Steps
| ||||||||||||||
New Application Tier Replacement Category: Core Funding
Milestones
RAG Status GREEN | Report by Adam Wadee for October 2014
Achievements in Last Period
Issues
Next Steps
| ||||||||||||||
|
Environment Monitoring System Category: Core Funding
Milestones
RAG Status GREEN | Report by Maurice Franceschi for October 2014With team members from ITI established, and Sheffield confirming a visit, and team members having good availability, project now on sure footing and looking good to achieve its aims. No concerns at present from anyone in the team. Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
| No projects closed |