April 2014

Report Date
April 2014

Infrastructure Programme Report for Programme Owner David Smyth

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

 

After the estimate for ITS103 Core technology Updates was increased substantially, the remaining project for this year was withdrawn, ten additional days were added to the programme budget, and the scope of the ITS103 reduced to allow the programme to deliver the key deliverables for the project whilst balancing the budget.

The programme effort estimated  is currently 15 days over the budget, almost all of this from PCode overspend. However, the six days estimate for PCode for the rest of the year will decrease, given only one project remains and the projects for next year have now been confirmed.

There are a number of actions from the INF104 for the programme to be aware of. These are listed in a dedicated page. https://www.projects.ed.ac.uk/programmepage/30193

 

 

 

 

 

 

 

 Section Two: Projects Not Started

Project InfoProgramme Manager's Commentary
  

Section Three: Projects in Progress

 

Project InfoProject Managers Commentary

ITS103 (AP34-038)

Core Technology Updates.

Category : C

 

 

Milestones

06-May-201411-Apr-2014Deployment Sign Off Review - NEWSDeliver
02-Jun-201419-Mar-2014ASOR APPSLIVEAccept
09-Jun-201426-Mar-2014Deploy APPS LIVEDeliver
23-Jun-201423-Jun-2014DSOR APPSDeliver
30-Jun-201418-Apr-2014ClosureClose

 

 

 

 

 

 

RAG Status

GREEN

 

 
Report by Morna Findlay for April 2014
 
Achievements This Period.
 
  • Acceptance review for NEWS migration achieved.
  • Delivery for NEWS migration achieved.
  • New scope, milestones and budget for project agreed and approved.
  • Status of testing in APPS checked.

 

Issues

  • evisitor not working in TEST - agree alternative sign off with OLL.

 

Next Steps

  • Deployment review for NEWS migration to be held.
  • UAT for APPS migration to re-start.
  • Acceptance Review for APPS migration to be held.
  • APPS migration to be delivered.

 

Programme Manager's Commentary

Morna has taken the project and reset it to realistic and achievable budget, timeline and deliverables, with a mixture of decent estimation, budget increase, descoping, review of team activities, and consultation with business contacts.

Programme Owner and Programme Manager have supported her with programme changes re. withdrawal of projects, descope and budget increase for the project, but this has been done having confidence in Morna's management of the project.

 

 

 

Section Four: Closed or Withdrawn Projects

 

 

Project InfoProject Managers Commentary

AP34-039

Development Tool Upgrades

Withdrawn on 30/8/13.

https://www.projects.ed.ac.uk/planning/project/141

This was due to impact on programme budget from carry over 12/13 projects.

However, we hope to be able to bring the project back into the 13/14 programme if budget, priority and new estimates allow.

 

The Division has built up reliance on a number of key products over the years to assist in project and service delivery.

This project would apply relevant upgrades to the following products:

JIRA

JIRA has fallen a few version behind latest version, so it may be this upgrade is required. Whether a proejct is required remain to be re-assessed.

 

Greenhopper

This is a small task to be done under APP004

 

Bamboo

This is a small task that should be covered by current Support arrangements.

 

 

ITS100

Implement New Database Tier

Report by David Watters

This project was closed on 13th September 2013

Please see the Completion Report for further information.

 

ITS101

SAN Migration

Report by Karen Stirling

This project was closed on 29th November 2013

Please see the Completion Report for further information.

ITS095

Upgrade of Oracle SOA Suite

Report by Stevie Conlon

The project was closed on the 7th November

Please see the Completion Report for further information.

INF104

Application Infrastructure Upgrade Project

Report by Maurice Franceschi

The project was closed on 4th April. Completion Report available.  

AP34-041 Business Data Recovery and Storage Implementation

Report by Maurice Franceschi

 

This project has been withdrawn, April 2014.

https://www.projects.ed.ac.uk/planning/project/140

This proposal will implement the findings of the review of data recovery and storage requirements for IS Applications as part of a wider review by ITI. The review will have outlined the requirements for storage of business data for disaster recovery/backup, archival and replication purposes. The necessary technical infrastructure will have been provisioned during 12/13 period as a result of the review and this proposal will bring the Applications service under the revised process and facilities.

Tony Weir will be developing the brief. The work is temporarily on hold due to conflicts with other priority work, but Tony has confirmed that it will happen in first half of 2014, and that it will be a procurement followed by an installation. The IS Apps effort involved for each project needs re-estimated. Currently this is a Small budget proposal.

The project has been withdrawn as there has been no progress from ITI, there is less time to complete the project in the current year, and there is now no budget available due to the increase in the ITS103 budget.