February 2014
- Report Date
- February 2014
Infrastructure Programme Report for Programme Owner David Smyth
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Programme Manager has also noticed a 12 day discrepancy between the projects' total effort and actual programme budget, so this may reduce the actual overrun to 6 days.
The main risk is to the not started Business Data Recovery proposal.
There are a number of actions from the INF104 for the programme to be aware of. These will be chronicled in a dedicated page.
https://www.projects.ed.ac.uk/programmepage/30193


Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
| AP34-041 Business Data Recovery and Storage Implementation |
https://www.projects.ed.ac.uk/planning/project/140 This proposal will implement the findings of the review of data recovery and storage requirements for IS Applications as part of a wider review by ITI. The review will have outlined the requirements for storage of business data for disaster recovery/backup, archival and replication purposes. The necessary technical infrastructure will have been provisioned during 12/13 period as a result of the review and this proposal will bring the Applications service under the revised process and facilities. Tony Weir will be developing the brief. The work is temporarily on hold due to conflicts with other priority work, but Tony has confirmed that it will happen in first half of 2014, and that it will be a procurement followed by an installation. The IS Apps effort involved for each project needs re-estimated. Currently this is a Small budget proposal. Status of this is now set as RED as there has been no progress from ITI.
|
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||
ITS103 (AP34-038) Core Technology Updates. Category : C
Milestones Programme Manager : No dates can be confirmed at this point.
RAG Status RED
| Report completed by Stevie Conlon for February 2014 Achievements This Period.
Issues
Next Steps
The project is marked as RED as dates for go-live on NEWS and APPS are still unclear and budget may need to be revisited. Programme Manager : budget is overrun and there looks to be substantial unplanned effort needed to resolve UAT issues. Programme Manager is looking to handover project to new project manager soon as possible so new PM can get a good handover from Steve and replan the UAT and Delivery and manage the budget issue. Programme Manager has asked to meet the team on Monday 10th March, and has asked for all Jiras to have been updated/closed by then, all off-the-piste issues raised as Jiras, and effort for all outstanding fixes estimated. Also that users for APPS and NEWS both be updated by PM as to cancellation of delivery.
| ||||||
INF104 Application Infrastructure Upgrade Project Category: Complience Milestones
RAG Status AMBER | Achievements in Last Period
Issues
Next Steps
RAG Status is Amber due to actual effort being 3 days over the approved budget. PM, Programme Manager and Programme Owner to resolve budget issue in March.
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
AP34-039 Development Tool Upgrades | Withdrawn on 30/8/13. https://www.projects.ed.ac.uk/planning/project/141 This was due to impact on programme budget from carry over 12/13 projects. However, we hope to be able to bring the project back into the 13/14 programme if budget, priority and new estimates allow.
The Division has built up reliance on a number of key products over the years to assist in project and service delivery. This project would apply relevant upgrades to the following products: JIRA JIRA has fallen a few version behind latest version, so it may be this upgrade is required. Whether a proejct is required remain to be re-assessed.
Greenhopper This is a small task to be done under APP004
Bamboo This is a small task that should be covered by current Support arrangements.
|
Implement New Database Tier | Report by David Watters This project was closed on 13th September 2013 Please see the Completion Report for further information.
|
ITS101 SAN Migration | Report by Karen Stirling This project was closed on 29th November 2013 Please see the Completion Report for further information. |
ITS095 Upgrade of Oracle SOA Suite | Report by Stevie Conlon The project was closed on the 7th November Please see the Completion Report for further information. |
